pennsylvania datacenter infrastructure
published: December 30, 2025updated: August 24, 2026โข
on this page
Pennsylvania datacenter infrastructure
Pennsylvania hosts 12 documented datacenter projects representing $125.0B in disclosed investment and 16.9 GW of power capacity. The state has emerged as a hub for AI/ML infrastructure, attracting hyperscaler investment. Multiple hyperscale operators have established presence in the state.
Snapshot note. The counts, investment and capacity figures on this page come from the wikiโs project dataset as it stood in December 2025, and have not been refreshed since. US datacenter announcements grew substantially through 2026, so treat these as a floor rather than a current tally. See data sources for methodology.
key statistics
| Total Projects | 12 |
| Total Investment | $125.0B |
| Total Power Capacity | 16.9 GW |
| Total Square Footage | 12,500,000 sq ft |
| Major Projects (>$1B or >500MW) | 11 |
project status breakdown
| Status | Projects | Percentage |
| Planned | 10 | 83.3% |
| Under Construction | 2 | 16.7% |
major projects
Top projects by investment and power capacity:
| Project | Location | Investment | Power | Status |
| Google PJM Data Center Infrastructure | Various locations in Pennsylvania, Various | $25.0B | 670 MW | Planned |
| Blackstone-QTS Northeastern Pennsylvania Data Centers | Northeastern Pennsylvania (Multiple Sites), Various | $25.0B | 0 MW | Planned |
| Amazon Web Services AI Innovation Campuses | Salem Township and Falls Township, Luzerne County and Bucks County | $20.0B | 960 MW | Under Construction |
| Pennsylvania Digital I (PAX) | Carlisle, Cumberland County | $15.0B | 1.4 GW | Planned |
| Gouldsboro Data Center Campus | Gouldsboro (Clifton and Covington Townships), Lackawanna County | $14.2B | 1.5 GW | Planned |
| Homer City Energy Campus | Homer City, Indiana County | $10.0B | 4.5 GW | Planned |
| CoreWeave Lancaster County AI Data Center | Lancaster, Lancaster County | $6.0B | 100 MW | Planned |
| York 2 Energy Center Data Campus | Peach Bottom Township, York County | $5.0B | 828 MW | Planned |
| Shippingport Power Station and Data Center | Shippingport, Beaver County | $3.2B | 2.7 GW | Planned |
| Microsoft Three Mile Island Energy Supply | Londonderry Township, Dauphin County | $1.6B | 835 MW | Planned |
regional distribution
| Region | Projects | Percentage |
| Northeastern Pennsylvania | 3 | 25.0% |
| Western Pennsylvania | 3 | 25.0% |
| South Central Pennsylvania | 3 | 25.0% |
| Central Pennsylvania | 1 | 8.3% |
| Southeastern Pennsylvania | 1 | 8.3% |
| Statewide | 1 | 8.3% |
key developers and operators
top sponsors
| Sponsor | Projects |
| Amazon Web Services | 1 |
| Amazon | 1 |
| Pennsylvania Data Center Partners | 1 |
| PowerHouse Data Centers | 1 |
| TECfusions | 1 |
| Homer City Redevelopment | 1 |
| Kiewit Power Constructors | 1 |
| CoreWeave | 1 |
| Chirisa Technology Parks | 1 |
| Machine Investment Group | 1 |
top operators
| Operator | Projects |
| Amazon Web Services | 1 |
| Pennsylvania Data Center Partners | 1 |
| PowerHouse Data Centers | 1 |
| TECfusions | 1 |
| Homer City Redevelopment | 1 |
| CoreWeave | 1 |
| 1778 Rich Pike LLC | 1 |
| Calpine Corporation | 1 |
| QTS Realty Trust | 1 |
| Frontier Group of Companies | 1 |
project types
| Purpose | Count |
| ai-ml | 8 |
| cloud | 4 |
| colocation | 1 |
| hyperscale | 8 |
complete project listing
All 12 documented projects in Pennsylvania:
Click to expand full project table
| Project | Location | Status | Investment | Power | Sponsors |
| Google PJM Data Center Infrastructure | Various locations in Pennsylvania, Various | Planned | $25.0B | 670 MW | Google, Alphabet |
| Blackstone-QTS Northeastern Pennsylvania Data Centers | Northeastern Pennsylvania (Multiple Sites), Various | Planned | $25.0B | 0 MW | Blackstone, QTS Realty Trust |
| Amazon Web Services AI Innovation Campuses | Salem Township and Falls Township, Luzerne County and Bucks County | Under Construction | $20.0B | 960 MW | Amazon Web Services, Amazon |
| Pennsylvania Digital I (PAX) | Carlisle, Cumberland County | Planned | $15.0B | 1.4 GW | Pennsylvania Data Center Partners, PowerHouse Data Centers |
| Gouldsboro Data Center Campus | Gouldsboro (Clifton and Covington Townships), Lackawanna County | Planned | $14.2B | 1.5 GW | 1778 Rich Pike LLC, Quantm Group LLC |
| Homer City Energy Campus | Homer City, Indiana County | Planned | $10.0B | 4.5 GW | Homer City Redevelopment, Kiewit Power Constructors |
| CoreWeave Lancaster County AI Data Center | Lancaster, Lancaster County | Planned | $6.0B | 100 MW | CoreWeave, Chirisa Technology Parks, Machine Investment Group |
| York 2 Energy Center Data Campus | Peach Bottom Township, York County | Planned | $5.0B | 828 MW | Energy Capital Partners, Calpine Corporation |
| Shippingport Power Station and Data Center | Shippingport, Beaver County | Planned | $3.2B | 2.7 GW | Frontier Group of Companies |
| Microsoft Three Mile Island Energy Supply | Londonderry Township, Dauphin County | Planned | $1.6B | 835 MW | Constellation Energy, Microsoft |
| TECfusions Keystone Connect | Upper Burrell, Westmoreland County | Under Construction | $0 | 3.0 GW | TECfusions |
| fifteenfortyseven Chester County Hyperscale Campus | East Whiteland Township, Chester County | Planned | $0 | 450 MW | fifteenfortyseven Critical Systems Realty, Green Fig Land Company |
related pages
data current as of December 2025