data center projects database
on this page
Data Center Projects Database
This page provides a comprehensive view of all 604 data center projects tracked in our database, representing over $1123B in total investment and 131,731MW of power capacity.
Dataset snapshot note (August 2026). Figures on this page derive from the wikiโs project dataset as it stood in December 2025 (604-609 tracked projects). That dataset has not been refreshed since, and the US pipeline grew substantially through 2026 โ treat counts, investment and capacity totals here as a floor, and any share or percentage computed against them as approximate. Kansas and Missouri totals were separately corrected in August 2026 after seven Kansas City metro projects were found filed under the wrong state; see state rankings.
Overview Statistics
| Total Projects | 604 |
| Total Investment | $1123.4B (236 projects) |
| Total Power Capacity | 131,731MW (325 projects) |
| Total Square Footage | 800M sq ft |
| Operational | 264 |
| Under Construction | 127 |
| Planned | 155 |
Distribution by Investment Tier
| Mega-Projects ($10B+) | 35 |
| Large Projects ($1-10B) | 119 |
| Medium Projects ($100M-1B) | 56 |
| Small Projects (under $100M) | 31 |
| Data Not Available | 368 |
Distribution by Purpose
| Hyperscale | 344 |
| Colocation | 285 |
| Cloud | 191 |
| AI/ML | 140 |
| Enterprise | 81 |
| Edge | 24 |
Top States by Project Count
| Virginia | 40 |
| Illinois | 28 |
| Texas | 27 |
| California | 25 |
| Georgia | 25 |
| Arizona | 22 |
| New Jersey | 22 |
| Nevada | 20 |
Top Sponsors
| Microsoft | 28 |
| 39 | |
| Amazon Web Services | 20 |
| Digital Realty | 20 |
| Meta | 11 |
| Equinix | 14 |
Mega-Projects (>$10B Investment)
These 35 projects represent the largest data center investments in the United States, each exceeding $10 billion in capital expenditure.
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Project Jupiter (Stargate Santa Teresa Campus) | New Mexico | under-construction | $165.0B | N/A | BorderPlex Digital Assets, STACK Infrastructure | ai-ml, hyperscale, +1 |
| Project Kestrel | Kansas | planned | $100.0B | N/A | Hunt Midwest | hyperscale |
| Stargate Project - Abilene Campus (Oracle/Crusoe) | Texas | operational | $40.0B | 1,200 | OpenAI, Oracle, +3 | hyperscale, ai-ml, +1 |
| Vermaland La Osa Data Center Park | Arizona | planned | $33.0B | 3,000 | Vermaland LLC | hyperscale, ai-ml |
| Tract Mooresville Technology Park | North Carolina | canceled | $30.0B | N/A | Tract | hyperscale |
| Hassayampa Ranch Data Center Campus | Arizona | planned | $25.0B | 1,500 | N/A | hyperscale, ai-ml |
| Blackstone-QTS Northeastern Pennsylvania Data Centers | Pennsylvania | planned | $25.0B | N/A | Blackstone, QTS Realty Trust | hyperscale |
| Google PJM Data Center Infrastructure | Pennsylvania | planned | $25.0B | 670 | Google, Alphabet | cloud, ai-ml |
| Vantage Data Centers - Frontier Campus | Texas | under-construction | $25.0B | 1,400 | Vantage Data Centers | hyperscale, ai-ml |
| Prince William Digital Gateway | Virginia | canceled | $24.7B | 2,700 | QTS Realty Trust, Compass Datacenters | hyperscale |
| Tract Buckeye Data Center Park | Arizona | planned | $20.0B | 1,800 | Tract | hyperscale, ai-ml |
| Amazon Web Services AI Innovation Campuses | Pennsylvania | under-construction | $20.0B | 960 | Amazon Web Services, Amazon | hyperscale, cloud, +1 |
| Energy Storage Solutions AI Data Center Campus | North Carolina | announced | $19.2B | 300 | Energy Storage Solutions | hyperscale, ai-ml |
| Project Bunkhouse | Georgia | planned | $19.0B | 1,830 | Digital Realty | hyperscale |
| Project Sail | Georgia | planned | $17.0B | 936 | Atlas Development LLC, Prologis | hyperscale |
| EdgeCore Louisa County Campus | Virginia | announced | $17.0B | 1,100 | EdgeCore Digital Infrastructure | hyperscale |
| T5 Data Centers - Georgia Campus | Georgia | planned | $16.0B | 1,200 | T5 Data Centers | hyperscale |
| AWS Madison County Data Center Campus | Mississippi | under-construction | $16.0B | 650 | Amazon Web Services | hyperscale, cloud |
| Applied Digital Toronto AI Data Center | South Dakota | planned | $16.0B | 430 | Applied Digital | ai-ml, hyperscale, +1 |
| Amazon AWS US West (Oregon) Region - Boardman | Oregon | operational | $15.0B | N/A | Amazon Web Services | hyperscale, cloud |
| Pennsylvania Digital I (PAX) | Pennsylvania | planned | $15.0B | 1,350 | Pennsylvania Data Center Partners, PowerHouse Data Centers | hyperscale, ai-ml |
| Project Marvel - Bessemer Hyperscale Data Center | Alabama | planned | $14.5B | 1,200 | Logistics Land Investments LLC | hyperscale |
| Gouldsboro Data Center Campus | Pennsylvania | planned | $14.2B | 1,500 | 1778 Rich Pike LLC, Quantm Group LLC | hyperscale |
| Red Wolf DCD Properties Data Center Campus | Kansas | planned | $12.6B | 600 | Red Wolf DCD Properties LLC | hyperscale |
| Amazon Web Services (AWS) New Carlisle Campus | Indiana | operational | $11.0B | 2,250 | Amazon Web Services, Clayco | hyperscale, cloud |
| AWS Louisa County Campus 1 | Virginia | under-construction | $11.0B | N/A | Amazon Web Services | hyperscale, cloud |
| AWS US East (Ohio) Region | Ohio | expansion | $10.3B | 1,204 | Amazon Web Services | cloud, hyperscale |
| Project Washington | Delaware | planned | $10.0B | 1,200 | Starwood Digital Ventures, Starwood Capital Group, +2 | colocation, hyperscale |
| Compass Datacenters - Hoffman Estates (Former Sears HQ) | Illinois | under-construction | $10.0B | 500 | Compass Datacenters | hyperscale, cloud |
| QTS - Cedar Rapids Campus | Iowa | under-construction | $10.0B | N/A | QTS Realty Trust, Blackstone | hyperscale, colocation |
| Project Mica (Google AI Campus) | Kansas | planned | $10.0B | 700 | Google LLC, AG Rose Solutions LLC, +1 | hyperscale, ai-ml, +1 |
| Meta Richland Parish AI Data Center (Hyperion Campus) | Louisiana | under-construction | $10.0B | 2,000 | Meta Platforms, Inc. | hyperscale, ai-ml |
| Compass Datacenters Meridian Campus | Mississippi | under-construction | $10.0B | 500 | Compass Datacenters | hyperscale, colocation |
| Amazon Web Services (AWS) Richmond County Campus | North Carolina | under-construction | $10.0B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Homer City Energy Campus | Pennsylvania | planned | $10.0B | 4,500 | Homer City Redevelopment, Kiewit Power Constructors | hyperscale, ai-ml |
Large Projects ($1-10B Investment)
These 119 projects represent major data center investments between $1 billion and $10 billion.
Top 50 by Investment
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Google Mayes County (Pryor) Data Center Expansion | Oklahoma | expansion | $9.0B | N/A | Google LLC | hyperscale, cloud, +1 |
| Vantage Data Centers - Port Washington | Wisconsin | planned | $8.0B | 1,300 | Vantage Data Centers | hyperscale, colocation |
| Digital Crossroads Hammond Expansion | Indiana | expansion | $7.0B | 200 | Decennial Group, Digital Crossroads | colocation, ai-ml, +1 |
| Related Digital Saline Township Campus | Michigan | planned | $7.0B | N/A | Related Companies, Related Digital, +2 | hyperscale, ai-ml, +1 |
| Cologix Johnstown Campus | Ohio | planned | $7.0B | 800 | Cologix | hyperscale, ai-ml, +1 |
| Tract - Project Tripletail | Utah | planned | $7.0B | 400 | Tract | hyperscale |
| Google - Council Bluffs Campus (Expansions) | Iowa | expansion | $6.8B | N/A | hyperscale, cloud | |
| Google Central Ohio Campuses | Ohio | operational | $6.7B | N/A | cloud, hyperscale | |
| Stream Data Centers STAMP Campus | New York | announced | $6.3B | 250 | Stream Data Centers | hyperscale |
| Project Lincoln (OC Data Center) | Kentucky | planned | $6.0B | 600 | Western Hospitality Partners | hyperscale |
| AVAIO Digital Taurus Data Center Hub | Mississippi | under-construction | $6.0B | 116 | AVAIO Digital Partners | ai-ml, cloud, +1 |
| CoreWeave Lancaster County AI Data Center | Pennsylvania | planned | $6.0B | 100 | CoreWeave, Chirisa Technology Parks, +1 | ai-ml, cloud |
| Amazon Web Services - Butts County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Amazon Web Services - Douglas County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Newton County Technology Park (Social Circle Technology Park) | Georgia | planned | $5.0B | N/A | TPA Group | hyperscale |
| Wiscasset Data Center (Proposed) | Maine | announced | $5.0B | N/A | Unknown (under NDA) | hyperscale, ai-ml |
| Quantum Frederick Campus | Maryland | under-construction | $5.0B | 2,000 | TPG Real Estate, Quantum Loophole (former) | hyperscale, colocation |
| Tract Farmington Technology Park | Minnesota | under-construction | $5.0B | N/A | Tract | colocation, hyperscale |
| Apple Maiden Data Center | North Carolina | operational | $5.0B | N/A | Apple | hyperscale, enterprise |
| York 2 Energy Center Data Campus | Pennsylvania | planned | $5.0B | 828 | Energy Capital Partners, Calpine Corporation | hyperscale |
| Advance Phase LLC Walla Walla Campus (Project Tree) | Washington | planned | $5.0B | N/A | Advance Phase LLC (Fortune 500 company alias) | hyperscale |
| Monarch Cloud Campus (Fidelis New Energy) | West Virginia | planned | $5.0B | 1,000 | Fidelis New Energy | hyperscale, ai-ml |
| Meta Lebanon LEAP District Campus | Indiana | planned | $4.8B | N/A | Meta | hyperscale, ai-ml |
| Project Springbank | Georgia | planned | $4.5B | 432 | Atlas Development LLC | hyperscale |
| Project Clydesdale (Tulsa County/Owasso) | Oklahoma | planned | $4.5B | N/A | Beale Infrastructure, Unknown hyperscaler | hyperscale, cloud |
| Google Berkeley County Data Center Campus | South Carolina | expansion | $4.5B | N/A | Google LLC | hyperscale, cloud, +1 |
| Google West Memphis Data Center (Project Pyramid) | Arkansas | under-construction | $4.0B | N/A | Google LLC | hyperscale, ai-ml, +1 |
| CoreWeave/Core Scientific Muskogee Data Center | Oklahoma | under-construction | $4.0B | 100 | CoreWeave, Core Scientific | hyperscale, ai-ml, +1 |
| ECP & KKR - Bosque County Campus | Texas | under-construction | $4.0B | 190 | Energy Capital Partners, KKR | hyperscale |
| Microsoft Data Center Expansion Phase 2 - Mount Pleasant | Wisconsin | announced | $4.0B | N/A | Microsoft | ai-ml, hyperscale, +1 |
| Amazon AWS Project Blue (Tucson) | Arizona | canceled | $3.6B | 600 | Amazon Web Services | cloud, hyperscale |
| Microsoft Fairwater AI Data Center - Mount Pleasant | Wisconsin | under-construction | $3.3B | N/A | Microsoft | ai-ml, hyperscale, +1 |
| Shippingport Power Station and Data Center | Pennsylvania | planned | $3.2B | 2,700 | Frontier Group of Companies | colocation, ai-ml |
| De Soto Data Center Campus (Project Pilot) | Kansas | planned | $3.1B | N/A | Mount Sunflower Properties, LLC, Beale Infrastructure, +1 | hyperscale |
| Novva Data Centers Mesa Campus | Arizona | planned | $3.0B | 300 | Novva Data Centers | hyperscale, colocation |
| Apollo Project - Helena Harbor Data Center | Arkansas | planned | $3.0B | 1,000 | Stadium Partners, Garrison Data Partners | hyperscale, ai-ml |
| Westfield Data Center Campus (Servistar Realties) | Massachusetts | planned | $3.0B | 150 | Servistar Realties | hyperscale |
| Vantage Data Centers NV1 Campus | Nevada | under-construction | $3.0B | 224 | Vantage Data Centers | hyperscale, ai-ml |
| TerraScale Energos Reno | Nevada | planned | $3.0B | 500 | TerraScale | hyperscale, enterprise |
| Applied Digital Polaris Forge 2 | North Dakota | under-construction | $3.0B | 280 | Applied Digital Corporation | ai-ml, hyperscale |
| Van Wert Mega Site Data Center | Ohio | planned | $3.0B | 500 | Thor Equities Group | hyperscale |
| Google Stillwater Data Center Campus | Oklahoma | under-construction | $3.0B | N/A | Google LLC | hyperscale, cloud, +1 |
| CleanArc Virginia Hyperscale Campus | Virginia | under-construction | $3.0B | 900 | CleanArc Data Centers | hyperscale |
| QTS Data Centers - Vienna (Dane County) | Wisconsin | planned | $3.0B | N/A | QTS Data Centers | hyperscale, colocation |
| Project Moc-1 (NorthMark Strategies) | South Carolina | planned | $2.8B | N/A | NorthMark Strategies | ai-ml, research |
| CloudHQ ORD Campus - Mount Prospect | Illinois | under-construction | $2.5B | 252 | CloudHQ | hyperscale |
| Meta - Altoona Data Center Campus | Iowa | operational | $2.5B | 260 | Meta | hyperscale, cloud |
| Hut 8 West Feliciana AI Data Center | Louisiana | under-construction | $2.5B | 1,000 | Hut 8 Corp. | hyperscale, ai-ml |
| Meta Sarpy Data Center Campus | Nebraska | operational | $2.5B | N/A | Meta Platforms, Inc. | hyperscale, cloud |
| Google Montgomery County Data Center | Tennessee | operational | $2.5B | N/A | Google LLC | hyperscale, cloud, +1 |
View all 119 large projects
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Google Mayes County (Pryor) Data Center Expansion | Oklahoma | expansion | $9.0B | N/A | Google LLC | hyperscale, cloud, +1 |
| Vantage Data Centers - Port Washington | Wisconsin | planned | $8.0B | 1,300 | Vantage Data Centers | hyperscale, colocation |
| Digital Crossroads Hammond Expansion | Indiana | expansion | $7.0B | 200 | Decennial Group, Digital Crossroads | colocation, ai-ml, +1 |
| Related Digital Saline Township Campus | Michigan | planned | $7.0B | N/A | Related Companies, Related Digital, +2 | hyperscale, ai-ml, +1 |
| Cologix Johnstown Campus | Ohio | planned | $7.0B | 800 | Cologix | hyperscale, ai-ml, +1 |
| Tract - Project Tripletail | Utah | planned | $7.0B | 400 | Tract | hyperscale |
| Google - Council Bluffs Campus (Expansions) | Iowa | expansion | $6.8B | N/A | hyperscale, cloud | |
| Google Central Ohio Campuses | Ohio | operational | $6.7B | N/A | cloud, hyperscale | |
| Stream Data Centers STAMP Campus | New York | announced | $6.3B | 250 | Stream Data Centers | hyperscale |
| Project Lincoln (OC Data Center) | Kentucky | planned | $6.0B | 600 | Western Hospitality Partners | hyperscale |
| AVAIO Digital Taurus Data Center Hub | Mississippi | under-construction | $6.0B | 116 | AVAIO Digital Partners | ai-ml, cloud, +1 |
| CoreWeave Lancaster County AI Data Center | Pennsylvania | planned | $6.0B | 100 | CoreWeave, Chirisa Technology Parks, +1 | ai-ml, cloud |
| Amazon Web Services - Butts County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Amazon Web Services - Douglas County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Newton County Technology Park (Social Circle Technology Park) | Georgia | planned | $5.0B | N/A | TPA Group | hyperscale |
| Wiscasset Data Center (Proposed) | Maine | announced | $5.0B | N/A | Unknown (under NDA) | hyperscale, ai-ml |
| Quantum Frederick Campus | Maryland | under-construction | $5.0B | 2,000 | TPG Real Estate, Quantum Loophole (former) | hyperscale, colocation |
| Tract Farmington Technology Park | Minnesota | under-construction | $5.0B | N/A | Tract | colocation, hyperscale |
| Apple Maiden Data Center | North Carolina | operational | $5.0B | N/A | Apple | hyperscale, enterprise |
| York 2 Energy Center Data Campus | Pennsylvania | planned | $5.0B | 828 | Energy Capital Partners, Calpine Corporation | hyperscale |
| Advance Phase LLC Walla Walla Campus (Project Tree) | Washington | planned | $5.0B | N/A | Advance Phase LLC (Fortune 500 company alias) | hyperscale |
| Monarch Cloud Campus (Fidelis New Energy) | West Virginia | planned | $5.0B | 1,000 | Fidelis New Energy | hyperscale, ai-ml |
| Meta Lebanon LEAP District Campus | Indiana | planned | $4.8B | N/A | Meta | hyperscale, ai-ml |
| Project Springbank | Georgia | planned | $4.5B | 432 | Atlas Development LLC | hyperscale |
| Project Clydesdale (Tulsa County/Owasso) | Oklahoma | planned | $4.5B | N/A | Beale Infrastructure, Unknown hyperscaler | hyperscale, cloud |
| Google Berkeley County Data Center Campus | South Carolina | expansion | $4.5B | N/A | Google LLC | hyperscale, cloud, +1 |
| Google West Memphis Data Center (Project Pyramid) | Arkansas | under-construction | $4.0B | N/A | Google LLC | hyperscale, ai-ml, +1 |
| CoreWeave/Core Scientific Muskogee Data Center | Oklahoma | under-construction | $4.0B | 100 | CoreWeave, Core Scientific | hyperscale, ai-ml, +1 |
| ECP & KKR - Bosque County Campus | Texas | under-construction | $4.0B | 190 | Energy Capital Partners, KKR | hyperscale |
| Microsoft Data Center Expansion Phase 2 - Mount Pleasant | Wisconsin | announced | $4.0B | N/A | Microsoft | ai-ml, hyperscale, +1 |
| Amazon AWS Project Blue (Tucson) | Arizona | canceled | $3.6B | 600 | Amazon Web Services | cloud, hyperscale |
| Microsoft Fairwater AI Data Center - Mount Pleasant | Wisconsin | under-construction | $3.3B | N/A | Microsoft | ai-ml, hyperscale, +1 |
| Shippingport Power Station and Data Center | Pennsylvania | planned | $3.2B | 2,700 | Frontier Group of Companies | colocation, ai-ml |
| De Soto Data Center Campus (Project Pilot) | Kansas | planned | $3.1B | N/A | Mount Sunflower Properties, LLC, Beale Infrastructure, +1 | hyperscale |
| Novva Data Centers Mesa Campus | Arizona | planned | $3.0B | 300 | Novva Data Centers | hyperscale, colocation |
| Apollo Project - Helena Harbor Data Center | Arkansas | planned | $3.0B | 1,000 | Stadium Partners, Garrison Data Partners | hyperscale, ai-ml |
| Westfield Data Center Campus (Servistar Realties) | Massachusetts | planned | $3.0B | 150 | Servistar Realties | hyperscale |
| Vantage Data Centers NV1 Campus | Nevada | under-construction | $3.0B | 224 | Vantage Data Centers | hyperscale, ai-ml |
| TerraScale Energos Reno | Nevada | planned | $3.0B | 500 | TerraScale | hyperscale, enterprise |
| Applied Digital Polaris Forge 2 | North Dakota | under-construction | $3.0B | 280 | Applied Digital Corporation | ai-ml, hyperscale |
| Van Wert Mega Site Data Center | Ohio | planned | $3.0B | 500 | Thor Equities Group | hyperscale |
| Google Stillwater Data Center Campus | Oklahoma | under-construction | $3.0B | N/A | Google LLC | hyperscale, cloud, +1 |
| CleanArc Virginia Hyperscale Campus | Virginia | under-construction | $3.0B | 900 | CleanArc Data Centers | hyperscale |
| QTS Data Centers - Vienna (Dane County) | Wisconsin | planned | $3.0B | N/A | QTS Data Centers | hyperscale, colocation |
| Project Moc-1 (NorthMark Strategies) | South Carolina | planned | $2.8B | N/A | NorthMark Strategies | ai-ml, research |
| CloudHQ ORD Campus - Mount Prospect | Illinois | under-construction | $2.5B | 252 | CloudHQ | hyperscale |
| Meta - Altoona Data Center Campus | Iowa | operational | $2.5B | 260 | Meta | hyperscale, cloud |
| Hut 8 West Feliciana AI Data Center | Louisiana | under-construction | $2.5B | 1,000 | Hut 8 Corp. | hyperscale, ai-ml |
| Meta Sarpy Data Center Campus | Nebraska | operational | $2.5B | N/A | Meta Platforms, Inc. | hyperscale, cloud |
| Google Montgomery County Data Center | Tennessee | operational | $2.5B | N/A | Google LLC | hyperscale, cloud, +1 |
| Google The Dalles Data Center Campus | Oregon | expansion | $2.4B | N/A | Google LLC | hyperscale, cloud |
| Meta Los Lunas Data Center Campus | New Mexico | expansion | $2.2B | 40 | Meta Platforms (Facebook) | hyperscale, ai-ml, +1 |
| Google Fort Wayne Data Center | Indiana | under-construction | $2.0B | N/A | hyperscale, cloud, +1 | |
| Vantage OH1 Campus | Ohio | under-construction | $2.0B | 192 | Vantage Data Centers | hyperscale, colocation |
| Meta Prineville Data Center Campus | Oregon | operational | $2.0B | 350 | Meta Platforms (Facebook) | hyperscale, cloud |
| Novva Data Centers - West Jordan Campus | Utah | under-construction | $2.0B | 175 | Novva Data Centers, CIM Group | hyperscale, ai-ml |
| Atlas Power Data Center | North Dakota | under-construction | $1.9B | 700 | FX Solutions Inc., Atlas Power Holdings ND, LLC | other |
| Microsoft - Union City Campus | Georgia | under-construction | $1.8B | 324 | Microsoft | hyperscale, cloud |
| Meta Henrico White Oak Campus | Virginia | operational | $1.7B | N/A | Meta | hyperscale |
| Google Pine Hill Business Campus Data Center | South Carolina | under-construction | $1.6B | N/A | Google LLC | hyperscale, cloud, +1 |
| Google Winding Woods Commerce Park Data Center | South Carolina | under-construction | $1.6B | N/A | Google LLC | hyperscale, cloud, +1 |
| Microsoft Three Mile Island Energy Supply | Pennsylvania | planned | $1.6B | 835 | Constellation Energy, Microsoft | cloud, ai-ml |
| Meta Montgomery Data Center | Alabama | under-construction | $1.5B | N/A | Meta Platforms, Inc. | hyperscale, ai-ml, +1 |
| Meta Huntsville Data Center | Alabama | operational | $1.5B | N/A | Meta Platforms, Inc. | hyperscale, cloud |
| Vantage Data Centers Phoenix Campus | Arizona | under-construction | $1.5B | 176 | Vantage Data Centers | colocation, hyperscale |
| Diode Ventures Harper Road Technology Park (Peculiar) | Missouri | canceled | $1.5B | N/A | Diode Ventures | hyperscale |
| Niagara Digital Campus | New York | planned | $1.5B | 140 | Niagara Falls Redevelopment (NFR), Urbacon Data Centre Solutions | ai-ml, colocation |
| Meta Prometheus (New Albany Campus) | Ohio | under-construction | $1.5B | 1,000 | Meta | hyperscale, ai-ml |
| QTS New Albany Campus | Ohio | under-construction | $1.5B | 222 | QTS Data Centers, Blackstone | colocation, hyperscale |
| Meta Gallatin Data Center Campus | Tennessee | operational | $1.5B | 500 | Meta Platforms Inc. | hyperscale, ai-ml |
| Meta - Fort Worth Data Center Campus | Texas | operational | $1.5B | N/A | Meta | hyperscale, enterprise |
| Meta Eagle Mountain Data Center | Utah | operational | $1.5B | 504 | Meta Platforms, Inc. | hyperscale, cloud |
| NSA Utah Data Center (Bumblehive) | Utah | operational | $1.5B | 65 | National Security Agency, U.S. Department of Defense | government |
| Microsoft Azure Data Centers - Cheyenne | Wyoming | operational | $1.5B | N/A | Microsoft | cloud, hyperscale |
| Microsoft - Medina County Data Centers | Texas | under-construction | $1.4B | N/A | Microsoft | cloud, hyperscale |
| Apple - Waukee Data Center Campus | Iowa | operational | $1.3B | 40 | Apple | hyperscale, cloud |
| TAC Data Centers - Project Cardinal | Montana | planned | $1.2B | 600 | Ardent TAC Data Centers | hyperscale, ai-ml, +1 |
| Google - Douglas County Campus | Georgia | operational | $1.2B | N/A | hyperscale, cloud | |
| University of Michigan & Los Alamos National Laboratory Data Center | Michigan | announced | $1.2B | N/A | University of Michigan, Los Alamos National Laboratory | research, ai-ml |
| EdgeCore Reno Campus | Nevada | under-construction | $1.2B | 216 | EdgeCore Digital Infrastructure, Partners Group | hyperscale, colocation |
| CoreWeave NEST Campus | New Jersey | under-construction | $1.2B | N/A | CoreWeave, Onyx Equities, +1 | ai-ml, cloud, +1 |
| Google Lenoir Data Center | North Carolina | operational | $1.2B | N/A | hyperscale, cloud | |
| CyrusOne & Calpine - DFW10 Whitney Campus | Texas | under-construction | $1.2B | 190 | CyrusOne, Calpine | hyperscale |
| Google - Eagle Mountain Land Acquisition | Utah | planned | $1.2B | N/A | Google LLC | hyperscale, cloud |
| BlackChamber Virginia Portfolio | Virginia | under-construction | $1.2B | 740 | BlackChamber Group | hyperscale, colocation |
| Related Digital Data Center (CoreWeave Campus) | Wyoming | under-construction | $1.2B | 302 | Related Digital | colocation, ai-ml, +1 |
| Google - Monroe County Campus | Georgia | planned | $1.1B | N/A | hyperscale, cloud | |
| Google Bridgeport Data Center | Alabama | operational | $1.0B | N/A | Google LLC | hyperscale, cloud |
| Meta Mesa Data Center | Arizona | under-construction | $1.0B | N/A | Meta | hyperscale, cloud |
| Google Mesa Data Center (Redhawk) | Arizona | under-construction | $1.0B | N/A | cloud, hyperscale | |
| Little Rock Port Data Center (Willowbend Capital) | Arkansas | planned | $1.0B | N/A | Willowbend Capital LLC, Unknown Fortune 100 Company | hyperscale |
| Conway Data Center (Forgelight Ventures) | Arkansas | planned | $1.0B | N/A | Forgelight Ventures LLC, Unknown Fortune 100 Company | hyperscale |
| QTS Aurora-Denver Data Center | Colorado | under-construction | $1.0B | 177 | QTS Realty Trust | hyperscale, cloud |
| Meta - Newton County Campus (Stanton Springs) | Georgia | expansion | $1.0B | N/A | Meta | hyperscale |
| Microsoft - Project Firecracker (Rome/Floyd County) | Georgia | planned | $1.0B | N/A | Microsoft | hyperscale, cloud |
| QTS - Project Excalibur (Fayetteville) | Georgia | under-construction | $1.0B | N/A | QTS Realty Trust, Blackstone | hyperscale, colocation |
| Diode Ventures Gemstone Technology Park | Idaho | planned | $1.0B | N/A | Diode Ventures, Black & Veatch | hyperscale, cloud |
| Meta DeKalb Data Center Campus | Illinois | operational | $1.0B | 200 | Meta Platforms Inc. (Facebook) | hyperscale, cloud |
| Google Franklin Township Data Center (Withdrawn) | Indiana | canceled | $1.0B | N/A | hyperscale, cloud | |
| Microsoft La Porte Data Center | Indiana | planned | $1.0B | N/A | Microsoft | cloud, ai-ml |
| Morgan County Data Center (Project Louie) | Indiana | planned | $1.0B | N/A | Undisclosed | hyperscale |
| Hancock County MegaSite (Withdrawn) | Indiana | canceled | $1.0B | N/A | Surge Development LLC | hyperscale |
| Meta Kansas City Data Center (Golden Plains Technology Park) | Kansas | operational | $1.0B | N/A | Meta Platforms, Inc. | hyperscale, cloud |
| Google Kansas City Data Center (Hunt Midwest Business Center) | Kansas | under-construction | $1.0B | 400 | Google LLC, Alphabet Inc. | hyperscale, cloud |
| Patmos AI Campus (Kansas City Star Building) | Kansas | expansion | $1.0B | 100 | Patmos | colocation, ai-ml |
| Mason County Technology Campus | Kentucky | planned | $1.0B | 2,200 | Fortune 100 Company (undisclosed) | hyperscale |
| Howell Township Data Center Campus | Michigan | planned | $1.0B | N/A | Stantec Consulting Michigan Inc., Randee LLC, +1 | hyperscale |
| Form8tion Augusta Township Data Center | Michigan | announced | $1.0B | N/A | Thor Equities, Form8tion, +1 | hyperscale |
| Google Kansas City Data Center | Missouri | under-construction | $1.0B | 400 | hyperscale, cloud | |
| Meta Kansas City Data Center (Golden Plains Technology Park) | Missouri | operational | $1.0B | 750 | Meta (Facebook), Diode Ventures | hyperscale, cloud |
| Apple Reno Data Center | Nevada | operational | $1.0B | N/A | Apple | cloud, enterprise |
| Microsoft Catawba County Campus | North Carolina | under-construction | $1.0B | N/A | Microsoft | hyperscale, cloud |
| Microsoft Licking County Campuses | Ohio | planned | $1.0B | N/A | Microsoft | cloud, hyperscale |
| QTS York County Data Center Campus | South Carolina | announced | $1.0B | N/A | QTS Realty Trust | hyperscale, colocation |
| GigaPop Data Center | Texas | planned | $1.0B | N/A | Gigabit Fiber, Lincoln Property Co., +1 | colocation, hyperscale |
| Blueprint Projects - Taylor Data Center | Texas | under-construction | $1.0B | N/A | Blueprint Projects | colocation |
| Microsoft East Wenatchee Campus | Washington | under-construction | $1.0B | N/A | Microsoft | hyperscale, cloud, +1 |
| Vantage Data Centers Quincy Campus (WA1) | Washington | operational | $1.0B | 89 | Vantage Data Centers | hyperscale, colocation |
| Meta Platforms Data Center - Beaver Dam | Wisconsin | under-construction | $1.0B | N/A | Meta Platforms | ai-ml, hyperscale, +1 |
High Power Projects (>500MW)
These 79 projects have power capacity exceeding 500MW, representing the most power-intensive data center deployments.
Top 50 by Power Capacity
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| New Era Energy & Digital AI Data Center Campus | New Mexico | announced | N/A | 7,000 | New Era Energy & Digital | ai-ml, hyperscale |
| Data City Texas | Texas | planned | N/A | 5,000 | Energy Abundance Development Corp | hyperscale, ai-ml |
| Homer City Energy Campus | Pennsylvania | planned | $10.0B | 4,500 | Homer City Redevelopment, Kiewit Power Constructors | hyperscale, ai-ml |
| Delta Gigasite / Fibernet MercuryDelta | Utah | planned | N/A | 4,000 | Fibernet MercuryDelta LLC, Creekstone Energy, +1 | hyperscale, ai-ml |
| Joule Capital Partners - Millard County Campus | Utah | planned | N/A | 4,000 | Joule Capital Partners | hyperscale, ai-ml |
| Cloverleaf Infrastructure Data Center Campus - Port Washington | Wisconsin | planned | N/A | 3,500 | Cloverleaf Infrastructure | hyperscale |
| Vermaland La Osa Data Center Park | Arizona | planned | $33.0B | 3,000 | Vermaland LLC | hyperscale, ai-ml |
| TECfusions Keystone Connect | Pennsylvania | under-construction | N/A | 3,000 | TECfusions | hyperscale, ai-ml |
| Shippingport Power Station and Data Center | Pennsylvania | planned | $3.2B | 2,700 | Frontier Group of Companies | colocation, ai-ml |
| Prince William Digital Gateway | Virginia | canceled | $24.7B | 2,700 | QTS Realty Trust, Compass Datacenters | hyperscale |
| Adams Fork Data Center Energy Campus - Harless Site | West Virginia | planned | N/A | 2,400 | TransGas Development Systems LLC | hyperscale |
| Adams Fork Data Center Energy Campus - Wharncliffe Site | West Virginia | planned | N/A | 2,400 | TransGas Development Systems LLC | hyperscale |
| Amazon Web Services (AWS) New Carlisle Campus | Indiana | operational | $11.0B | 2,250 | Amazon Web Services, Clayco | hyperscale, cloud |
| Mason County Technology Campus | Kentucky | planned | $1.0B | 2,200 | Fortune 100 Company (undisclosed) | hyperscale |
| Meta Richland Parish AI Data Center (Hyperion Campus) | Louisiana | under-construction | $10.0B | 2,000 | Meta Platforms, Inc. | hyperscale, ai-ml |
| Quantum Frederick Campus | Maryland | under-construction | $5.0B | 2,000 | TPG Real Estate, Quantum Loophole (former) | hyperscale, colocation |
| Project Bunkhouse | Georgia | planned | $19.0B | 1,830 | Digital Realty | hyperscale |
| Tract Buckeye Data Center Park | Arizona | planned | $20.0B | 1,800 | Tract | hyperscale, ai-ml |
| Pioneer Development - Yorkville Project Cardinal | Illinois | planned | N/A | 1,800 | Pioneer Development, LLC | hyperscale |
| PowerHouse & Provident - Grand Prairie Campus | Texas | under-construction | N/A | 1,800 | PowerHouse Data Centers, Provident | hyperscale, ai-ml |
| Crusoe/Tallgrass AI Data Center | Wyoming | announced | N/A | 1,800 | Crusoe Energy Systems, Tallgrass Energy | ai-ml, hyperscale |
| CloudHQ LC Campus | Virginia | operational | N/A | 1,700 | CloudHQ | hyperscale |
| Fundamental Data Tucker County Data Center | West Virginia | under-construction | N/A | 1,656 | Fundamental Data LLC | hyperscale |
| Tract Silver Springs Data Center Park | Nevada | planned | N/A | 1,600 | Tract | hyperscale, ai-ml |
| Hassayampa Ranch Data Center Campus | Arizona | planned | $25.0B | 1,500 | N/A | hyperscale, ai-ml |
| Gouldsboro Data Center Campus | Pennsylvania | planned | $14.2B | 1,500 | 1778 Rich Pike LLC, Quantm Group LLC | hyperscale |
| Prometheus Hyperscale - Natrona/Converse County Campus | Wyoming | planned | $500M | 1,500 | Prometheus Hyperscale, Spiritus, +1 | ai-ml, hyperscale |
| Vantage Data Centers - Frontier Campus | Texas | under-construction | $25.0B | 1,400 | Vantage Data Centers | hyperscale, ai-ml |
| Pennsylvania Digital I (PAX) | Pennsylvania | planned | $15.0B | 1,350 | Pennsylvania Data Center Partners, PowerHouse Data Centers | hyperscale, ai-ml |
| Vantage Data Centers - Port Washington | Wisconsin | planned | $8.0B | 1,300 | Vantage Data Centers | hyperscale, colocation |
| Zenith Volts Roswell Data Center | New Mexico | planned | N/A | 1,250 | Zenith Volts Corporation | ai-ml, cloud, +1 |
| AWS US East (Ohio) Region | Ohio | expansion | $10.3B | 1,204 | Amazon Web Services | cloud, hyperscale |
| Project Marvel - Bessemer Hyperscale Data Center | Alabama | planned | $14.5B | 1,200 | Logistics Land Investments LLC | hyperscale |
| Project Washington | Delaware | planned | $10.0B | 1,200 | Starwood Digital Ventures, Starwood Capital Group, +2 | colocation, hyperscale |
| T5 Data Centers - Georgia Campus | Georgia | planned | $16.0B | 1,200 | T5 Data Centers | hyperscale |
| T5 @ Chicago IV - Grayslake Campus | Illinois | planned | N/A | 1,200 | T5 Data Centers | hyperscale, ai-ml, +1 |
| Tract South Valley Technology Park | Nevada | planned | N/A | 1,200 | Tract | hyperscale, ai-ml |
| Stargate Project - Abilene Campus (Oracle/Crusoe) | Texas | operational | $40.0B | 1,200 | OpenAI, Oracle, +3 | hyperscale, ai-ml, +1 |
| Prometheus Hyperscale - WY-1 (Evanston Campus) | Wyoming | under-construction | N/A | 1,200 | Prometheus Hyperscale | hyperscale, ai-ml |
| EdgeCore Louisa County Campus | Virginia | announced | $17.0B | 1,100 | EdgeCore Digital Infrastructure | hyperscale |
| Apollo Project - Helena Harbor Data Center | Arkansas | planned | $3.0B | 1,000 | Stadium Partners, Garrison Data Partners | hyperscale, ai-ml |
| COPT Defense Properties - Van Meter Campus | Iowa | planned | N/A | 1,000 | COPT Defense Properties | hyperscale, cloud |
| Hut 8 West Feliciana AI Data Center | Louisiana | under-construction | $2.5B | 1,000 | Hut 8 Corp. | hyperscale, ai-ml |
| Quantica Infrastructure - Big Sky Digital Infrastructure Campus | Montana | announced | N/A | 1,000 | Quantica Infrastructure LLC, Big Sky Digital Infrastructure LLC | hyperscale, ai-ml, +1 |
| Meta Prometheus (New Albany Campus) | Ohio | under-construction | $1.5B | 1,000 | Meta | hyperscale, ai-ml |
| Monarch Cloud Campus (Fidelis New Energy) | West Virginia | planned | $5.0B | 1,000 | Fidelis New Energy | hyperscale, ai-ml |
| OpenAI Stargate Data Center - Wisconsin (Evaluation) | Wisconsin | planned | N/A | 1,000 | OpenAI, Oracle, +1 | ai-ml, hyperscale |
| Amazon Web Services AI Innovation Campuses | Pennsylvania | under-construction | $20.0B | 960 | Amazon Web Services, Amazon | hyperscale, cloud, +1 |
| Project Sail | Georgia | planned | $17.0B | 936 | Atlas Development LLC, Prologis | hyperscale |
| CleanArc Virginia Hyperscale Campus | Virginia | under-construction | $3.0B | 900 | CleanArc Data Centers | hyperscale |
AI/ML Data Centers
These 146 projects are specifically designed or optimized for AI and machine learning workloads.
Top 50 AI/ML Projects by Investment
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Project Jupiter (Stargate Santa Teresa Campus) | New Mexico | under-construction | $165.0B | N/A | BorderPlex Digital Assets, STACK Infrastructure | ai-ml, hyperscale, +1 |
| Stargate Project - Abilene Campus (Oracle/Crusoe) | Texas | operational | $40.0B | 1,200 | OpenAI, Oracle, +3 | hyperscale, ai-ml, +1 |
| Vermaland La Osa Data Center Park | Arizona | planned | $33.0B | 3,000 | Vermaland LLC | hyperscale, ai-ml |
| Hassayampa Ranch Data Center Campus | Arizona | planned | $25.0B | 1,500 | N/A | hyperscale, ai-ml |
| Google PJM Data Center Infrastructure | Pennsylvania | planned | $25.0B | 670 | Google, Alphabet | cloud, ai-ml |
| Vantage Data Centers - Frontier Campus | Texas | under-construction | $25.0B | 1,400 | Vantage Data Centers | hyperscale, ai-ml |
| Tract Buckeye Data Center Park | Arizona | planned | $20.0B | 1,800 | Tract | hyperscale, ai-ml |
| Amazon Web Services AI Innovation Campuses | Pennsylvania | under-construction | $20.0B | 960 | Amazon Web Services, Amazon | hyperscale, cloud, +1 |
| Energy Storage Solutions AI Data Center Campus | North Carolina | announced | $19.2B | 300 | Energy Storage Solutions | hyperscale, ai-ml |
| Applied Digital Toronto AI Data Center | South Dakota | planned | $16.0B | 430 | Applied Digital | ai-ml, hyperscale, +1 |
| Pennsylvania Digital I (PAX) | Pennsylvania | planned | $15.0B | 1,350 | Pennsylvania Data Center Partners, PowerHouse Data Centers | hyperscale, ai-ml |
| Project Mica (Google AI Campus) | Kansas | planned | $10.0B | 700 | Google LLC, AG Rose Solutions LLC, +1 | hyperscale, ai-ml, +1 |
| Meta Richland Parish AI Data Center (Hyperion Campus) | Louisiana | under-construction | $10.0B | 2,000 | Meta Platforms, Inc. | hyperscale, ai-ml |
| Amazon Web Services (AWS) Richmond County Campus | North Carolina | under-construction | $10.0B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Homer City Energy Campus | Pennsylvania | planned | $10.0B | 4,500 | Homer City Redevelopment, Kiewit Power Constructors | hyperscale, ai-ml |
| Google Mayes County (Pryor) Data Center Expansion | Oklahoma | expansion | $9.0B | N/A | Google LLC | hyperscale, cloud, +1 |
| Digital Crossroads Hammond Expansion | Indiana | expansion | $7.0B | 200 | Decennial Group, Digital Crossroads | colocation, ai-ml, +1 |
| Related Digital Saline Township Campus | Michigan | planned | $7.0B | N/A | Related Companies, Related Digital, +2 | hyperscale, ai-ml, +1 |
| Cologix Johnstown Campus | Ohio | planned | $7.0B | 800 | Cologix | hyperscale, ai-ml, +1 |
| AVAIO Digital Taurus Data Center Hub | Mississippi | under-construction | $6.0B | 116 | AVAIO Digital Partners | ai-ml, cloud, +1 |
| CoreWeave Lancaster County AI Data Center | Pennsylvania | planned | $6.0B | 100 | CoreWeave, Chirisa Technology Parks, +1 | ai-ml, cloud |
| Amazon Web Services - Butts County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Amazon Web Services - Douglas County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Wiscasset Data Center (Proposed) | Maine | announced | $5.0B | N/A | Unknown (under NDA) | hyperscale, ai-ml |
| Monarch Cloud Campus (Fidelis New Energy) | West Virginia | planned | $5.0B | 1,000 | Fidelis New Energy | hyperscale, ai-ml |
| Meta Lebanon LEAP District Campus | Indiana | planned | $4.8B | N/A | Meta | hyperscale, ai-ml |
| Google Berkeley County Data Center Campus | South Carolina | expansion | $4.5B | N/A | Google LLC | hyperscale, cloud, +1 |
| Google West Memphis Data Center (Project Pyramid) | Arkansas | under-construction | $4.0B | N/A | Google LLC | hyperscale, ai-ml, +1 |
| CoreWeave/Core Scientific Muskogee Data Center | Oklahoma | under-construction | $4.0B | 100 | CoreWeave, Core Scientific | hyperscale, ai-ml, +1 |
| Microsoft Data Center Expansion Phase 2 - Mount Pleasant | Wisconsin | announced | $4.0B | N/A | Microsoft | ai-ml, hyperscale, +1 |
| Microsoft Fairwater AI Data Center - Mount Pleasant | Wisconsin | under-construction | $3.3B | N/A | Microsoft | ai-ml, hyperscale, +1 |
| Shippingport Power Station and Data Center | Pennsylvania | planned | $3.2B | 2,700 | Frontier Group of Companies | colocation, ai-ml |
| Apollo Project - Helena Harbor Data Center | Arkansas | planned | $3.0B | 1,000 | Stadium Partners, Garrison Data Partners | hyperscale, ai-ml |
| Vantage Data Centers NV1 Campus | Nevada | under-construction | $3.0B | 224 | Vantage Data Centers | hyperscale, ai-ml |
| Applied Digital Polaris Forge 2 | North Dakota | under-construction | $3.0B | 280 | Applied Digital Corporation | ai-ml, hyperscale |
| Google Stillwater Data Center Campus | Oklahoma | under-construction | $3.0B | N/A | Google LLC | hyperscale, cloud, +1 |
| Project Moc-1 (NorthMark Strategies) | South Carolina | planned | $2.8B | N/A | NorthMark Strategies | ai-ml, research |
| Hut 8 West Feliciana AI Data Center | Louisiana | under-construction | $2.5B | 1,000 | Hut 8 Corp. | hyperscale, ai-ml |
| Google Montgomery County Data Center | Tennessee | operational | $2.5B | N/A | Google LLC | hyperscale, cloud, +1 |
| Meta Los Lunas Data Center Campus | New Mexico | expansion | $2.2B | 40 | Meta Platforms (Facebook) | hyperscale, ai-ml, +1 |
| Google Fort Wayne Data Center | Indiana | under-construction | $2.0B | N/A | hyperscale, cloud, +1 | |
| Novva Data Centers - West Jordan Campus | Utah | under-construction | $2.0B | 175 | Novva Data Centers, CIM Group | hyperscale, ai-ml |
| Google Pine Hill Business Campus Data Center | South Carolina | under-construction | $1.6B | N/A | Google LLC | hyperscale, cloud, +1 |
| Google Winding Woods Commerce Park Data Center | South Carolina | under-construction | $1.6B | N/A | Google LLC | hyperscale, cloud, +1 |
| Microsoft Three Mile Island Energy Supply | Pennsylvania | planned | $1.6B | 835 | Constellation Energy, Microsoft | cloud, ai-ml |
| Meta Montgomery Data Center | Alabama | under-construction | $1.5B | N/A | Meta Platforms, Inc. | hyperscale, ai-ml, +1 |
| Niagara Digital Campus | New York | planned | $1.5B | 140 | Niagara Falls Redevelopment (NFR), Urbacon Data Centre Solutions | ai-ml, colocation |
| Meta Prometheus (New Albany Campus) | Ohio | under-construction | $1.5B | 1,000 | Meta | hyperscale, ai-ml |
| Meta Gallatin Data Center Campus | Tennessee | operational | $1.5B | 500 | Meta Platforms Inc. | hyperscale, ai-ml |
| TAC Data Centers - Project Cardinal | Montana | planned | $1.2B | 600 | Ardent TAC Data Centers | hyperscale, ai-ml, +1 |
Projects by Status
Operational Projects (266)
Currently operational data centers.
View top 50 operational projects
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Meta Huntsville Data Center | Alabama | operational | $1.5B | N/A | Meta Platforms, Inc. | hyperscale, cloud |
| Google Bridgeport Data Center | Alabama | operational | $1.0B | N/A | Google LLC | hyperscale, cloud |
| DC BLOX Birmingham Data Center | Alabama | operational | N/A | N/A | DC BLOX | colocation |
| DC BLOX Huntsville (Existing) | Alabama | operational | N/A | N/A | DC BLOX | colocation, government |
| GCI Anchorage Data Center | Alaska | operational | N/A | N/A | GCI Communication Corp. | colocation, enterprise |
| Greensparc Cordova Edge Data Center | Alaska | operational | N/A | 0 | Greensparc, Cordova Electric Cooperative, +1 | edge, colocation |
| Microsoft West US 3 Azure Region | Arizona | operational | $258M | N/A | Microsoft | cloud, hyperscale |
| QTS Phoenix 2 Campus | Arizona | operational | N/A | 210 | QTS, Blackstone | colocation, hyperscale |
| NTT Global Data Centers Mesa Campus (Elliot Road) | Arizona | operational | N/A | 240 | NTT Global Data Centers | hyperscale, colocation |
| CyrusOne Phoenix-Chandler Campus | Arizona | operational | N/A | 81 | CyrusOne | colocation, hyperscale |
| Digital Realty PHX10 | Arizona | operational | N/A | 32 | Digital Realty | colocation |
| Digital Realty PHX15 | Arizona | operational | N/A | 54 | Digital Realty | colocation, ai-ml |
| TierPoint Little Rock Data Center | Arkansas | operational | N/A | N/A | TierPoint | colocation, enterprise |
| Ritter Communications Data Technology Center | Arkansas | operational | $8M | N/A | Ritter Communications | colocation, enterprise, +1 |
| Prime Data Centers Vernon (LAX01-01) | California | operational | N/A | N/A | Prime Data Centers | hyperscale, ai-ml |
| Equinix SV12x (xScale) | California | operational | N/A | 28 | Equinix, PGIM Real Estate | hyperscale |
| Equinix SV10 | California | operational | N/A | 14 | Equinix | colocation, cloud |
| CoreSite SV9 | California | operational | N/A | N/A | CoreSite | colocation, ai-ml |
| CoreSite LA3 | California | operational | N/A | 6 | CoreSite | colocation, ai-ml |
| T5 Los Angeles (El Segundo) | California | operational | N/A | 16 | T5 Data Centers | enterprise, colocation |
| CyrusOne Santa Clara (SCV1) | California | operational | N/A | 96 | CyrusOne | colocation, hyperscale |
| Digital Realty SC1 Santa Clara | California | operational | N/A | 60 | Digital Realty | colocation, cloud |
| Vantage Data Centers Santa Clara I (CA1) | California | operational | N/A | 77 | Vantage Data Centers | colocation, hyperscale |
| Vantage Data Centers Santa Clara II (CA2) | California | operational | N/A | 75 | Vantage Data Centers | colocation, hyperscale |
| QTS Sacramento (SAC1) | California | operational | N/A | 9 | QTS Data Centers | colocation |
| NTT Global Data Centers Sacramento Campus | California | operational | N/A | 53 | NTT Global Data Centers | colocation, cloud |
| Google Los Angeles Region | California | operational | N/A | N/A | cloud | |
| Microsoft Azure Fresno | California | operational | N/A | N/A | Microsoft Corporation | cloud |
| T5@Colorado Springs Data Center Campus | Colorado | operational | $800M | 100 | T5 Data Centers | enterprise, colocation |
| Iron Mountain Denver Data Center (DEN-1) | Colorado | operational | N/A | 14 | Iron Mountain | colocation, enterprise, +1 |
| H5 Data Centers Denver | Colorado | operational | N/A | 17 | H5 Data Centers | colocation, enterprise |
| RadiusDC 1500 Champa | Colorado | operational | N/A | 10 | Infrastructure and Power Innovations (IPI), RadiusDC | edge, colocation |
| CyrusOne NYM5 Norwalk Data Center | Connecticut | operational | $75M | 16 | Cervalis, Fortis Property Group | colocation, enterprise |
| Aphorio Carter Trumbull Data Center | Connecticut | operational | $10M | 15 | Aphorio Carter Critical Infrastructure Fund | colocation, enterprise |
| TierPoint Waterbury Data Center | Connecticut | operational | N/A | N/A | TierPoint | colocation, enterprise |
| DaSTOR New Castle Data Center | Delaware | operational | N/A | 8 | DaSTOR LLC | colocation, cloud, +1 |
| DaSTOR Wilmington CCC Data Center | Delaware | operational | N/A | 2 | DaSTOR LLC | colocation, enterprise |
| Data Canopy Newark Data Center | Delaware | operational | N/A | 6 | Data Canopy | colocation, enterprise |
| Lumen Wilmington Data Center | Delaware | operational | N/A | N/A | Lumen Technologies, Level 3 Communications, +1 | colocation, enterprise |
| Trijit Wilmington Data Center | Delaware | operational | N/A | N/A | Trijit Corporation | colocation, enterprise |
| Cologix Lakeland Data Center | Florida | operational | N/A | N/A | Cologix | colocation |
| Equinix Miami MI1 (NAP of the Americas) | Florida | operational | N/A | N/A | Equinix | colocation, cloud |
| Digital Realty Miami Data Center | Florida | operational | N/A | N/A | Digital Realty | colocation, cloud |
| QTS Miami Data Center | Florida | operational | N/A | N/A | QTS Data Centers | colocation |
| Google - Douglas County Campus | Georgia | operational | $1.2B | N/A | hyperscale, cloud | |
| DC BLOX - Atlanta West (Douglas County) | Georgia | operational | N/A | 80 | DC BLOX | hyperscale, colocation |
| CyrusOne - Douglas County Campus | Georgia | operational | $200M | 50 | CyrusOne | hyperscale, colocation, +2 |
| Digital Realty - ATL11 (Austell) | Georgia | operational | N/A | N/A | Digital Realty | colocation |
| Digital Realty - ATL13 (Downtown Atlanta) | Georgia | operational | N/A | 10 | Digital Realty | colocation |
| Digital Realty - ATL14 (Downtown Atlanta) | Georgia | operational | N/A | N/A | Digital Realty | colocation |
Under Construction (129)
Projects currently under construction.
View top 50 under construction
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Meta Montgomery Data Center | Alabama | under-construction | $1.5B | N/A | Meta Platforms, Inc. | hyperscale, ai-ml, +1 |
| University of Alabama High Performance Computing and Data Center | Alabama | under-construction | $96M | N/A | University of Alabama | research |
| Hilcorp Endicott Bitcoin Mining Pilot | Alaska | under-construction | N/A | 1 | Hilcorp Alaska, TA Infrastructure | other |
| Meta Mesa Data Center | Arizona | under-construction | $1.0B | N/A | Meta | hyperscale, cloud |
| Google Mesa Data Center (Redhawk) | Arizona | under-construction | $1.0B | N/A | cloud, hyperscale | |
| Vantage Data Centers Phoenix Campus | Arizona | under-construction | $1.5B | 176 | Vantage Data Centers | colocation, hyperscale |
| Edged Energy Mesa Data Center | Arizona | under-construction | $70M | 36 | Edged Energy | ai-ml, hyperscale |
| 5C Data Centers Phoenix Region (PHX01) | Arizona | under-construction | N/A | 20 | 5C Data Centers | colocation, ai-ml |
| Stream Data Centers Phoenix Campus | Arizona | under-construction | N/A | 280 | Stream Data Centers | hyperscale, colocation |
| Compass Datacenters Goodyear Campus | Arizona | under-construction | N/A | 350 | Compass Datacenters | hyperscale, colocation |
| Prime Data Centers Phoenix Campus | Arizona | under-construction | N/A | 240 | Prime Data Centers | hyperscale, colocation |
| Amazon AWS Phoenix Data Centers | Arizona | under-construction | N/A | N/A | Amazon Web Services | cloud, hyperscale |
| Google West Memphis Data Center (Project Pyramid) | Arkansas | under-construction | $4.0B | N/A | Google LLC | hyperscale, ai-ml, +1 |
| Microsoft San Jose Data Center | California | under-construction | N/A | 99 | Microsoft Corporation | cloud, hyperscale |
| STACK Infrastructure San Jose Expansion | California | under-construction | N/A | 60 | STACK Infrastructure | hyperscale |
| Vantage Data Centers Santa Clara III (CA3) | California | under-construction | N/A | 64 | Vantage Data Centers | colocation, hyperscale |
| EdgeCore Silicon Valley Campus | California | under-construction | N/A | 72 | EdgeCore Digital Infrastructure, Partners Group | hyperscale, cloud |
| QTS Aurora-Denver Data Center | Colorado | under-construction | $1.0B | 177 | QTS Realty Trust | hyperscale, cloud |
| CoreSite DE3 Denver Data Center | Colorado | under-construction | N/A | 18 | CoreSite (American Tower) | colocation, ai-ml, +1 |
| Flexential Parker Data Center | Colorado | under-construction | N/A | 22 | Flexential | colocation, ai-ml |
| HostDime Orlando Data Center | Florida | under-construction | $60M | 8 | HostDime | colocation, hyperscale |
| Iron Mountain Miami Data Center (MIA-1) | Florida | under-construction | N/A | 16 | Iron Mountain | colocation, ai-ml |
| DC BLOX Palm Coast Cable Landing Station & Data Center Campus | Florida | under-construction | N/A | N/A | DC BLOX, Google | colocation, cloud |
| Microsoft - East Point Campus | Georgia | under-construction | N/A | N/A | Microsoft | hyperscale, cloud |
| Microsoft - Palmetto Campus | Georgia | under-construction | N/A | N/A | Microsoft | hyperscale, cloud |
| Microsoft - Union City Campus | Georgia | under-construction | $1.8B | 324 | Microsoft | hyperscale, cloud |
| QTS - Project Excalibur (Fayetteville) | Georgia | under-construction | $1.0B | N/A | QTS Realty Trust, Blackstone | hyperscale, colocation |
| DC BLOX - Atlanta East (Rockdale County) | Georgia | under-construction | N/A | 144 | DC BLOX | hyperscale, colocation |
| AlohaNAP Expansion | Hawaii | under-construction | N/A | 3 | Harrison Street, fifteenfortyseven Critical Systems Realty (1547) | colocation, hyperscale, +1 |
| Meta Kuna Data Center | Idaho | under-construction | $900M | 200 | Meta Platforms Inc. | hyperscale, ai-ml, +1 |
| Compass Datacenters - Hoffman Estates (Former Sears HQ) | Illinois | under-construction | $10.0B | 500 | Compass Datacenters | hyperscale, cloud |
| CyrusOne Aurora Campus | Illinois | under-construction | $350M | 18 | CyrusOne | hyperscale, colocation |
| CloudHQ ORD Campus - Mount Prospect | Illinois | under-construction | $2.5B | 252 | CloudHQ | hyperscale |
| Microsoft Cherry Valley Campus | Illinois | under-construction | N/A | N/A | Microsoft | hyperscale, cloud |
| Stream Data Centers - Chicago III (ORDC) | Illinois | under-construction | N/A | 40 | Stream Data Centers | hyperscale, cloud |
| Iron Mountain CHI-1 | Illinois | under-construction | N/A | 36 | Iron Mountain | colocation, hyperscale |
| Google Fort Wayne Data Center | Indiana | under-construction | $2.0B | N/A | hyperscale, cloud, +1 | |
| Meta Jeffersonville Data Center | Indiana | under-construction | $800M | N/A | Meta, Turner Construction | hyperscale, ai-ml |
| Google - Cedar Rapids Campus | Iowa | under-construction | $576M | N/A | hyperscale, cloud, +1 | |
| QTS - Cedar Rapids Campus | Iowa | under-construction | $10.0B | N/A | QTS Realty Trust, Blackstone | hyperscale, colocation |
| Meta - Davenport Data Center Campus | Iowa | under-construction | $800M | N/A | Meta | hyperscale, cloud |
| Edged - Ankeny Data Center | Iowa | under-construction | $187M | 13 | Edged Data Centers | ai-ml, hyperscale |
| Google Kansas City Data Center (Hunt Midwest Business Center) | Kansas | under-construction | $1.0B | 400 | Google LLC, Alphabet Inc. | hyperscale, cloud |
| PowerHouse Data Centers Louisville Campus | Kentucky | under-construction | N/A | 400 | PowerHouse Data Centers, Poe Companies | hyperscale, cloud, +1 |
| Meta Richland Parish AI Data Center (Hyperion Campus) | Louisiana | under-construction | $10.0B | 2,000 | Meta Platforms, Inc. | hyperscale, ai-ml |
| Hut 8 West Feliciana AI Data Center | Louisiana | under-construction | $2.5B | 1,000 | Hut 8 Corp. | hyperscale, ai-ml |
| Green 4 Maine Data Center Campus | Maine | under-construction | N/A | N/A | Green 4 Maine, Tom Manning, +1 | hyperscale, ai-ml, +1 |
| Quantum Frederick Campus | Maryland | under-construction | $5.0B | 2,000 | TPG Real Estate, Quantum Loophole (former) | hyperscale, colocation |
| Rowan Digital Infrastructure - Bauxite I | Maryland | under-construction | $975M | 300 | Rowan Digital Infrastructure | hyperscale |
| Aligned Data Centers - Critical Digital Infrastructure Facility | Maryland | under-construction | N/A | 264 | Aligned Data Centers | hyperscale, colocation |
Planned Projects (154)
Projects in planning stages.
View top 50 planned projects
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Project Marvel - Bessemer Hyperscale Data Center | Alabama | planned | $14.5B | 1,200 | Logistics Land Investments LLC | hyperscale |
| DC BLOX Montgomery Data Center | Alabama | planned | $30M | 40 | DC BLOX | colocation, hyperscale, +1 |
| DC BLOX Huntsville Expansion | Alabama | planned | N/A | 5 | DC BLOX | colocation, hyperscale, +1 |
| AT&T Hoover Data Center Upgrade | Alabama | planned | $40M | N/A | AT&T | enterprise |
| Southern Company Birmingham Data Center | Alabama | planned | $20M | N/A | Southern Company | enterprise |
| Far North Digital Prudhoe Bay Data Center | Alaska | planned | N/A | 120 | Far North Digital, LLC | colocation, hyperscale |
| ExxonMobil Alaska Cryptocurrency Mining Initiative | Alaska | planned | N/A | N/A | ExxonMobil | other |
| Vermaland La Osa Data Center Park | Arizona | planned | $33.0B | 3,000 | Vermaland LLC | hyperscale, ai-ml |
| Hassayampa Ranch Data Center Campus | Arizona | planned | $25.0B | 1,500 | N/A | hyperscale, ai-ml |
| Tract Buckeye Data Center Park | Arizona | planned | $20.0B | 1,800 | Tract | hyperscale, ai-ml |
| Novva Data Centers Mesa Campus | Arizona | planned | $3.0B | 300 | Novva Data Centers | hyperscale, colocation |
| QTS Phoenix 3 Campus (Glendale) | Arizona | planned | N/A | 750 | QTS, Blackstone | hyperscale, colocation |
| NTT Global Data Centers Mesa Campus (Pecos & Crismon) | Arizona | planned | N/A | 360 | NTT Global Data Centers | hyperscale, colocation |
| Apollo Project - Helena Harbor Data Center | Arkansas | planned | $3.0B | 1,000 | Stadium Partners, Garrison Data Partners | hyperscale, ai-ml |
| Little Rock Port Data Center (Willowbend Capital) | Arkansas | planned | $1.0B | N/A | Willowbend Capital LLC, Unknown Fortune 100 Company | hyperscale |
| Conway Data Center (Forgelight Ventures) | Arkansas | planned | $1.0B | N/A | Forgelight Ventures LLC, Unknown Fortune 100 Company | hyperscale |
| Clarksville Data Center | Arkansas | planned | N/A | N/A | N/A | hyperscale |
| Arcadis/Terra Ventures San Jose Sustainable Data Center | California | planned | N/A | N/A | Arcadis, Terra Ventures | hyperscale |
| Amazon AWS Gilroy Data Center | California | planned | N/A | 100 | Amazon Data Services | cloud, hyperscale |
| CalEthos Lithium Valley Data Center Campus | California | planned | N/A | 420 | CalEthos | hyperscale, ai-ml |
| Prime Data Centers Sacramento Expansion (Building Two) | California | planned | N/A | 18 | Prime Data Centers | colocation, hyperscale |
| STACK Infrastructure Hayward (SVY03A) | California | planned | N/A | 77 | STACK Infrastructure | hyperscale |
| CyrusOne Naval Air Station Lemoore | California | planned | N/A | 100 | CyrusOne, Ameresco, +1 | ai-ml, government |
| Millstone Nuclear Data Center Campus | Connecticut | planned | N/A | 300 | NE Edge, Dominion Energy | hyperscale, cloud |
| Atlas Capital Group Bloomfield Data Center | Connecticut | planned | N/A | N/A | Atlas Capital Group, River Bend Development CT | hyperscale |
| Hartford AI Innovation Center | Connecticut | planned | $90M | N/A | City of Hartford, State of Connecticut | ai-ml, research |
| Wallingford Data Center Development | Connecticut | planned | N/A | N/A | Charter Development Group LLC | colocation |
| Project Washington | Delaware | planned | $10.0B | 1,200 | Starwood Digital Ventures, Starwood Capital Group, +2 | colocation, hyperscale |
| Osceola County Hyperscale Data Center Campus | Florida | planned | N/A | N/A | US Development | hyperscale |
| Project Apollo | Florida | planned | $150M | 15 | N/A | colocation |
| NextNRG Nassau County Data Center & Microgrid Campus | Florida | planned | N/A | 200 | NextNRG | hyperscale, ai-ml |
| Project Sail | Georgia | planned | $17.0B | 936 | Atlas Development LLC, Prologis | hyperscale |
| Project Springbank | Georgia | planned | $4.5B | 432 | Atlas Development LLC | hyperscale |
| Project Bunkhouse | Georgia | planned | $19.0B | 1,830 | Digital Realty | hyperscale |
| T5 Data Centers - Georgia Campus | Georgia | planned | $16.0B | 1,200 | T5 Data Centers | hyperscale |
| Amazon Web Services - Butts County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Amazon Web Services - Douglas County Campus | Georgia | planned | $5.5B | N/A | Amazon Web Services | hyperscale, cloud, +1 |
| Google - Monroe County Campus | Georgia | planned | $1.1B | N/A | hyperscale, cloud | |
| Microsoft - Project Firecracker (Rome/Floyd County) | Georgia | planned | $1.0B | N/A | Microsoft | hyperscale, cloud |
| Newton County Technology Park (Social Circle Technology Park) | Georgia | planned | $5.0B | N/A | TPA Group | hyperscale |
| Digital Realty - ATL15/ATL16 (Forest Park) | Georgia | planned | N/A | N/A | Digital Realty | hyperscale, colocation |
| Diode Ventures Gemstone Technology Park | Idaho | planned | $1.0B | N/A | Diode Ventures, Black & Veatch | hyperscale, cloud |
| ValorC3 Data Centers - Boise Facility 2 | Idaho | planned | N/A | 10 | ValorC3 Data Centers, DIF Capital Partners | colocation, enterprise, +1 |
| T5 Data Centers - Nampa | Idaho | planned | N/A | 8 | T5 Data Centers | enterprise, colocation |
| Idaho National Laboratory AI Data Center Initiative | Idaho | planned | N/A | N/A | U.S. Department of Energy | ai-ml, research |
| T5 @ Chicago IV - Grayslake Campus | Illinois | planned | N/A | 1,200 | T5 Data Centers | hyperscale, ai-ml, +1 |
| Pioneer Development - Yorkville Project Cardinal | Illinois | planned | N/A | 1,800 | Pioneer Development, LLC | hyperscale |
| Prologis - Yorkville Project Steel | Illinois | planned | N/A | N/A | Prologis, L.P. | hyperscale |
| Microsoft Plano Campus | Illinois | planned | N/A | N/A | Microsoft | hyperscale, cloud |
| Google Cloud - CME Group Aurora Private Cloud | Illinois | planned | N/A | N/A | Google Cloud, CME Group | enterprise, colocation, +1 |
Medium Projects ($100M-1B)
These 56 projects represent substantial investments between $100 million and $1 billion.
View all 56 medium projects
| Project Name | State | Status | Investment | Power (MW) | Sponsors | Purpose |
|---|---|---|---|---|---|---|
| Rowan Digital Infrastructure - Bauxite I | Maryland | under-construction | $975M | 300 | Rowan Digital Infrastructure | hyperscale |
| Meta Kuna Data Center | Idaho | under-construction | $900M | 200 | Meta Platforms Inc. | hyperscale, ai-ml, +1 |
| Switch SUPERNAP Grand Rapids Campus | Michigan | expansion | $900M | 320 | Switch Communications Group LLC | hyperscale, colocation |
| WhiteFiber NC-1 Madison Data Center | North Carolina | operational | $865M | 24 | WhiteFiber | ai-ml, hyperscale, +1 |
| T5@Colorado Springs Data Center Campus | Colorado | operational | $800M | 100 | T5 Data Centers | enterprise, colocation |
| Meta Jeffersonville Data Center | Indiana | under-construction | $800M | N/A | Meta, Turner Construction | hyperscale, ai-ml |
| Meta - Davenport Data Center Campus | Iowa | under-construction | $800M | N/A | Meta | hyperscale, cloud |
| Meta Rosemount Data Center | Minnesota | under-construction | $800M | N/A | Meta Platforms Inc. | hyperscale, ai-ml |
| Project Anthem (Tulsa East) | Oklahoma | planned | $800M | N/A | Unknown (believed to be Meta Platforms) | hyperscale, cloud |
| Meta Sage Mill Industrial Park Data Center | South Carolina | under-construction | $800M | N/A | Meta Platforms Inc. | hyperscale, ai-ml |
| Meta - Temple Data Center | Texas | under-construction | $800M | N/A | Meta | hyperscale, ai-ml |
| Meta Data Center (Project Cosmo) | Wyoming | under-construction | $800M | N/A | Meta Platforms | hyperscale, ai-ml, +1 |
| Meta Forest City Data Center Campus | North Carolina | operational | $750M | N/A | Meta Platforms | hyperscale, cloud |
| Google Becker Data Center | Minnesota | canceled | $600M | N/A | Google LLC | hyperscale, cloud |
| Google Papillion Data Center | Nebraska | operational | $600M | N/A | Google LLC | hyperscale, cloud |
| Google Lincoln Data Center (Agate Project) | Nebraska | under-construction | $600M | N/A | Google LLC, Agate LLC | hyperscale, cloud, +1 |
| Google Henderson Data Center | Nevada | operational | $600M | N/A | cloud, hyperscale | |
| Google Storey County Data Center | Nevada | operational | $600M | N/A | cloud, hyperscale | |
| Google - Midlothian Data Center | Texas | operational | $600M | N/A | cloud, hyperscale | |
| Google - Red Oak Data Center | Texas | under-construction | $600M | N/A | cloud, hyperscale, +1 | |
| Google - Cedar Rapids Campus | Iowa | under-construction | $576M | N/A | hyperscale, cloud, +1 | |
| Sabey Data Centers Umatilla Campus (SDC Umatilla) | Oregon | planned | $520M | 100 | Sabey Data Centers, National Real Estate Advisors | hyperscale, enterprise, +1 |
| Microsoft Azure North Central US - Northlake | Illinois | operational | $500M | N/A | Microsoft | hyperscale, cloud |
| Bitzero - Polson Facility | Montana | planned | $500M | 50 | Bitzero | other |
| Bitzero Nekoma Pyramid Data Center | North Dakota | under-construction | $500M | N/A | Bitzero Blockchain Inc., Cavalier County Job Development Authority | other |
| AWS Spotsylvania County Campus | Virginia | planned | $500M | N/A | Amazon Web Services | hyperscale, cloud |
| AWS Culpeper County Campus | Virginia | announced | $500M | N/A | Amazon Web Services | hyperscale, cloud |
| Prometheus Hyperscale - Natrona/Converse County Campus | Wyoming | planned | $500M | 1,500 | Prometheus Hyperscale, Spiritus, +1 | ai-ml, hyperscale |
| Stream Data Centers - San Antonio III | Texas | under-construction | $400M | 200 | Stream Data Centers | hyperscale, colocation |
| Cigna Windsor Data Center | Connecticut | expansion | $386M | N/A | Cigna Corporation | enterprise |
| CyrusOne Aurora Campus | Illinois | under-construction | $350M | 18 | CyrusOne | hyperscale, colocation |
| DC BLOX High Point Data Center | North Carolina | planned | $305M | 18 | DC BLOX | colocation, cloud |
| Nautilus Millinocket Data Center (Cancelled) | Maine | canceled | $300M | 60 | Nautilus Data Technologies | hyperscale, ai-ml |
| Microsoft West US 3 Azure Region | Arizona | operational | $258M | N/A | Microsoft | cloud, hyperscale |
| Metro Edge - Illinois Medical District | Illinois | planned | $257M | N/A | Metro Edge Development Partners | colocation |
| Microsoft - San Antonio Data Center Campus | Texas | expansion | $215M | N/A | Microsoft | cloud, hyperscale |
| Microsoft - West Des Moines Campus (6th Data Center) | Iowa | planned | $210M | N/A | Microsoft | hyperscale, cloud |
| Aligned NEO-01 Campus | Ohio | under-construction | $202M | 96 | Aligned Data Centers | hyperscale, ai-ml |
| NOVVA Colorado Springs Data Center Campus | Colorado | expansion | $200M | 30 | NOVVA Data Centers | colocation, hyperscale |
| CyrusOne - Douglas County Campus | Georgia | operational | $200M | 50 | CyrusOne | hyperscale, colocation, +2 |
| US Signal Detroit Metro Expansion | Michigan | expansion | $200M | 3 | US Signal, Igneo Infrastructure Partners | hyperscale, cloud, +3 |
| Evoque-Archer Nashville Campus | Tennessee | under-construction | $200M | 100 | Evoque Data Center Solutions, Archer Datacenters | colocation, hyperscale |
| CyrusOne DFW7 - Fort Worth | Texas | under-construction | $200M | 70 | CyrusOne | hyperscale, colocation |
| Edged - Ankeny Data Center | Iowa | under-construction | $187M | 13 | Edged Data Centers | ai-ml, hyperscale |
| Microsoft Malaga Campus | Washington | under-construction | $160M | N/A | Microsoft | hyperscale, cloud, +1 |
| Project Apollo | Florida | planned | $150M | 15 | N/A | colocation |
| TierPoint St. Louis Data Center | Missouri | under-construction | $150M | N/A | TierPoint | enterprise, colocation |
| Edged Data Centers Kansas City | Kansas | operational | $143M | 26 | Edged Energy, Evergy | colocation, ai-ml |
| Edged Kansas City Data Center | Missouri | operational | $143M | 26 | Edged | colocation, ai-ml |
| Skybox Datacenters - PowerCampus Austin | Texas | under-construction | $125M | 600 | Skybox Datacenters LLC | hyperscale, colocation |
| Deep Green Lansing DG06 Data Center | Michigan | announced | $120M | 24 | Deep Green, Lansing Board of Water & Light | colocation, ai-ml, +1 |
| Digital Realty - Garland Campus Expansion | Texas | under-construction | $120M | 48 | Digital Realty | colocation |
| Massachusetts State Springfield Data Center | Massachusetts | operational | $110M | N/A | Commonwealth of Massachusetts | government |
| FBI Grey Wolf Data Center | Idaho | operational | $100M | 5 | Federal Bureau of Investigation, U.S. Department of Justice | government |
| Core Scientific Grand Forks Data Center | North Dakota | operational | $100M | 100 | Core Scientific | other, ai-ml |
| Polaris Technologies Bitcoin Mining Data Center | Oklahoma | under-construction | $100M | 200 | Polaris Technologies Inc. | other |
Related Pages
- Mega-Projects Overview - Detailed analysis of projects >$10B
- AI/ML Data Centers - Deep dive into AI-optimized facilities
- Geographic Distribution - State-by-state analysis
- Sponsors & Operators - Key players in the industry
Data Collection Methodology
This database was compiled from:
- Public announcements and press releases from companies and government agencies
- News articles from technology and business publications
- Corporate investor relations materials
- State and local government economic development announcements
- Industry analyst reports and market research
Data Quality Notes
- Investment figures: 236 of 604 projects (39%) have confirmed investment data
- Power capacity: 325 of 604 projects (54%) have confirmed power capacity data
- Status: All projects include status information (operational, under construction, planned, announced, expansion, or canceled)
- Update frequency: Data is continuously updated as new information becomes available
Limitations
- Investment figures may represent total planned investment across multiple phases
- Power capacity figures may represent maximum planned capacity
- Some projects may have been announced but later canceled or delayed
- Geographic coordinates and specific addresses may not be available for all projects
- Purpose classifications may overlap (e.g., a facility can be both hyperscale and cloud)
Last updated: October 16, 2025