oklahoma datacenter infrastructure

published: October 16, 2025 โ€ข

Oklahoma datacenter infrastructure

Oklahoma hosts 9 documented datacenter projects representing $21.4B in disclosed investment and 310 MW of power capacity. The state has emerged as a hub for AI/ML infrastructure, attracting hyperscaler investment. Multiple hyperscale operators have established presence in the state.

key statistics

Total Projects9
Total Investment$21.4B
Total Power Capacity310 MW
Total Square Footage469,000 sq ft
Major Projects (>$1B or >500MW)4

project status breakdown

StatusProjectsPercentage
Expansion111.1%
Operational222.2%
Planned333.3%
Under Construction333.3%

major projects

Top projects by investment and power capacity:

ProjectLocationInvestmentPowerStatus
Google Mayes County (Pryor) Data Center ExpansionPryor, Mayes County$9.0BN/AExpansion
Project Clydesdale (Tulsa County/Owasso)Owasso, Tulsa County$4.5BN/APlanned
CoreWeave/Core Scientific Muskogee Data CenterMuskogee, Muskogee County$4.0B100 MWUnder Construction
Google Stillwater Data Center CampusStillwater, Payne County$3.0BN/AUnder Construction

regional distribution

RegionProjectsPercentage
Northeast Oklahoma333.3%
East Oklahoma222.2%
Central Oklahoma222.2%
North Central Oklahoma111.1%
Oklahoma (Sunbelt region)111.1%

key developers and operators

top sponsors

SponsorProjects
Google LLC2
Unknown (believed to be Meta Platforms)1
Beale Infrastructure1
Unknown hyperscaler1
CoreWeave1
Core Scientific1
Polaris Technologies Inc.1
Cerebras Systems1
Scale Datacenters1
TierPoint LLC1

top operators

OperatorProjects
Google LLC2
Unknown (believed to be Meta Platforms)1
Unknown (likely Google, Microsoft, Amazon, or Meta)1
Core Scientific1
Polaris Technologies Inc.1
Cerebras Systems1
TierPoint LLC1
EDGNEX Data Centers1

project types

PurposeCount
ai-ml5
cloud6
colocation1
enterprise1
hyperscale6
other1

complete project listing

All 9 documented projects in Oklahoma:

Click to expand full project table
ProjectLocationStatusInvestmentPowerSponsors
Google Mayes County (Pryor) Data Center ExpansionPryor, Mayes CountyExpansion$9.0BN/AGoogle LLC
Project Clydesdale (Tulsa County/Owasso)Owasso, Tulsa CountyPlanned$4.5BN/ABeale Infrastructure, Unknown hyperscaler
CoreWeave/Core Scientific Muskogee Data CenterMuskogee, Muskogee CountyUnder Construction$4.0B100 MWCoreWeave, Core Scientific
Google Stillwater Data Center CampusStillwater, Payne CountyUnder Construction$3.0BN/AGoogle LLC
Project Anthem (Tulsa East)Tulsa, Tulsa CountyPlanned$800MN/AUnknown (believed to be Meta Platforms)
Polaris Technologies Bitcoin Mining Data CenterMuskogee, Muskogee CountyUnder Construction$100M200 MWPolaris Technologies Inc.
TierPoint Oklahoma City Data Center ExpansionOklahoma City, Oklahoma CountyOperational$30MN/ATierPoint LLC
Cerebras Systems Oklahoma City AI Data CenterOklahoma City, Oklahoma CountyOperationalN/A10 MWCerebras Systems, Scale Datacenters
DAMAC/EDGNEX Oklahoma Data CentersUnknown, UnknownPlannedN/AN/ADAMAC Group, EDGNEX Data Centers

data current as of October 2025

on this page