ohio datacenter infrastructure

published: October 16, 2025 โ€ข

Ohio datacenter infrastructure

Ohio hosts 10 documented datacenter projects representing $33.2B in disclosed investment and 4.2 GW of power capacity. The state has emerged as a hub for AI/ML infrastructure, attracting hyperscaler investment. Multiple hyperscale operators have established presence in the state.

key statistics

Total Projects10
Total Investment$33.2B
Total Power Capacity4.2 GW
Total Square Footage15,787,757 sq ft
Major Projects (>$1B or >500MW)8

project status breakdown

StatusProjectsPercentage
Expansion110.0%
Operational110.0%
Planned330.0%
Under Construction550.0%

major projects

Top projects by investment and power capacity:

ProjectLocationInvestmentPowerStatus
AWS US East (Ohio) RegionNew Albany, Dublin, Hilliard, Sunbury, Franklin County, Delaware County$10.3B1.2 GWExpansion
Cologix Johnstown CampusJohnstown, Licking County$7.0B800 MWPlanned
Google Central Ohio CampusesNew Albany, Columbus, Lancaster, Franklin County, Fairfield County$6.7BN/AOperational
Van Wert Mega Site Data CenterVan Wert, Van Wert County$3.0B500 MWPlanned
Vantage OH1 CampusNew Albany, Franklin County$2.0B192 MWUnder Construction
Meta Prometheus (New Albany Campus)New Albany, Franklin County$1.5B1.0 GWUnder Construction
QTS New Albany CampusNew Albany, Franklin County$1.5B222 MWUnder Construction
Microsoft Licking County CampusesNew Albany, Heath, Hebron, Licking County$1.0BN/APlanned

regional distribution

RegionProjectsPercentage
Central Ohio880.0%
Northeast Ohio110.0%
Northwest Ohio110.0%

key developers and operators

top sponsors

SponsorProjects
Meta1
Google1
Amazon Web Services1
Microsoft1
Vantage Data Centers1
QTS Data Centers1
Blackstone1
Cologix1
5C Data Centers1
Aligned Data Centers1

top operators

OperatorProjects
Meta1
Google1
Amazon Web Services1
Microsoft Azure1
Vantage Data Centers1
QTS Data Centers1
Cologix1
5C Data Centers1
Aligned Data Centers1

project types

PurposeCount
ai-ml3
cloud4
colocation4
hyperscale10

complete project listing

All 10 documented projects in Ohio:

Click to expand full project table
ProjectLocationStatusInvestmentPowerSponsors
AWS US East (Ohio) RegionNew Albany, Dublin, Hilliard, Sunbury, Franklin County, Delaware CountyExpansion$10.3B1.2 GWAmazon Web Services
Cologix Johnstown CampusJohnstown, Licking CountyPlanned$7.0B800 MWCologix
Google Central Ohio CampusesNew Albany, Columbus, Lancaster, Franklin County, Fairfield CountyOperational$6.7BN/AGoogle
Van Wert Mega Site Data CenterVan Wert, Van Wert CountyPlanned$3.0B500 MWThor Equities Group
Vantage OH1 CampusNew Albany, Franklin CountyUnder Construction$2.0B192 MWVantage Data Centers
Meta Prometheus (New Albany Campus)New Albany, Franklin CountyUnder Construction$1.5B1.0 GWMeta
QTS New Albany CampusNew Albany, Franklin CountyUnder Construction$1.5B222 MWQTS Data Centers, Blackstone
Microsoft Licking County CampusesNew Albany, Heath, Hebron, Licking CountyPlanned$1.0BN/AMicrosoft
Aligned NEO-01 CampusPerkins Township (Sandusky area), Erie CountyUnder Construction$202M96 MWAligned Data Centers
5C Data Centers CMH01Springfield (Columbus area), Clark CountyUnder ConstructionN/A200 MW5C Data Centers

data current as of October 2025

on this page