north dakota datacenter infrastructure

published: October 16, 2025 โ€ข

North Dakota datacenter infrastructure

North Dakota hosts 9 documented datacenter projects representing $5.5B in disclosed investment and 2.3 GW of power capacity. The state has emerged as a hub for AI/ML infrastructure, attracting hyperscaler investment. Multiple hyperscale operators have established presence in the state.

key statistics

Total Projects9
Total Investment$5.5B
Total Power Capacity2.3 GW
Total Square Footage497,000 sq ft
Major Projects (>$1B or >500MW)4

project status breakdown

StatusProjectsPercentage
Operational555.6%
Planned111.1%
Under Construction333.3%

major projects

Top projects by investment and power capacity:

ProjectLocationInvestmentPowerStatus
Applied Digital Polaris Forge 2Harwood, Cass County$3.0B280 MWUnder Construction
Atlas Power Data CenterWilliston, Williams County$1.9B700 MWUnder Construction
Applied Digital Polaris Forge 1Ellendale, Dickey CountyN/A530 MWOperational
Rainbow Energy Coal Creek Data Center ParkUnderwood, McLean CountyN/A500 MWPlanned

regional distribution

RegionProjectsPercentage
Central North Dakota333.3%
Eastern North Dakota222.2%
Southeastern North Dakota111.1%
Western North Dakota111.1%
Northern North Dakota111.1%
North Dakota111.1%

key developers and operators

top sponsors

SponsorProjects
Applied Digital Corporation3
FX Solutions Inc.1
Atlas Power Holdings ND, LLC1
Bitzero Blockchain Inc.1
Cavalier County Job Development Authority1
Core Scientific1
Rainbow Energy Center, LLC1
Rainbow Energy Marketing Corp.1
Cathedra Bitcoin1

top operators

OperatorProjects
Applied Digital Corporation3
Atlas Power1
Bitzero Blockchain Inc.1
Core Scientific1
Rainbow Energy Center, LLC1
Rainbow Energy Marketing Corp.1
Cathedra Bitcoin1

project types

PurposeCount
ai-ml4
hyperscale3
other6

complete project listing

All 9 documented projects in North Dakota:

Click to expand full project table
ProjectLocationStatusInvestmentPowerSponsors
Applied Digital Polaris Forge 2Harwood, Cass CountyUnder Construction$3.0B280 MWApplied Digital Corporation
Atlas Power Data CenterWilliston, Williams CountyUnder Construction$1.9B700 MWFX Solutions Inc., Atlas Power Holdings ND, LLC
Bitzero Nekoma Pyramid Data CenterNekoma, Cavalier CountyUnder Construction$500MN/ABitzero Blockchain Inc., Cavalier County Job Development Authority
Core Scientific Grand Forks Data CenterGrand Forks, Grand Forks CountyOperational$100M100 MWCore Scientific
Applied Digital Polaris Forge 1Ellendale, Dickey CountyOperationalN/A530 MWApplied Digital Corporation
Rainbow Energy Coal Creek Data Center ParkUnderwood, McLean CountyPlannedN/A500 MWRainbow Energy Center, LLC
Applied Digital JMS01Jamestown, Stutsman CountyOperationalN/A106 MWApplied Digital Corporation
Cathedra Bitcoin North Dakota FacilityUnknown, UnknownOperationalN/A60 MWCathedra Bitcoin
Rainbow Energy Bismarck Data CenterBismarck, Burleigh CountyOperationalN/AN/ARainbow Energy Marketing Corp.

data current as of October 2025