Georgia hosts 25 documented datacenter projects representing $79.8B in disclosed investment and 5.0 GW of power capacity. The state has emerged as a hub for AI/ML infrastructure, attracting hyperscaler investment. Multiple hyperscale operators have established presence in the state.
key statistics
| Total Projects | 25 |
| Total Investment | $79.8B |
| Total Power Capacity | 5.0 GW |
| Total Square Footage | 36,283,200 sq ft |
| Major Projects (>$1B or >500MW) | 13 |
project status breakdown
| Status | Projects | Percentage |
| Expansion | 1 | 4.0% |
| Operational | 9 | 36.0% |
| Planned | 10 | 40.0% |
| Under Construction | 5 | 20.0% |
major projects
Top projects by investment and power capacity:
| Project | Location | Investment | Power | Status |
| Project Bunkhouse | Stilesboro, Bartow | $19.0B | 1.8 GW | Planned |
| Project Sail | Newnan, Coweta | $17.0B | 936 MW | Planned |
| T5 Data Centers - Georgia Campus | Undisclosed, Unknown | $16.0B | 1.2 GW | Planned |
| Amazon Web Services - Butts County Campus | Jackson, Butts | $5.5B | N/A | Planned |
| Amazon Web Services - Douglas County Campus | Douglasville, Douglas | $5.5B | N/A | Planned |
| Newton County Technology Park (Social Circle Technology Park) | Social Circle, Newton | $5.0B | N/A | Planned |
| Project Springbank | Adairsville, Bartow | $4.5B | 432 MW | Planned |
| Microsoft - Union City Campus | Union City, Fulton | $1.8B | 324 MW | Under Construction |
| Google - Douglas County Campus | Lithia Springs, Douglas | $1.2B | N/A | Operational |
| Google - Monroe County Campus | Forsyth, Monroe | $1.1B | N/A | Planned |
regional distribution
| Region | Projects | Percentage |
| South Metro Atlanta | 6 | 24.0% |
| West Metro Atlanta | 5 | 20.0% |
| Downtown Atlanta | 4 | 16.0% |
| East Metro Atlanta | 3 | 12.0% |
| Northwest Metro Atlanta | 2 | 8.0% |
| Georgia | 1 | 4.0% |
| Southeast Metro Atlanta | 1 | 4.0% |
| Central Georgia | 1 | 4.0% |
| Northwest Georgia | 1 | 4.0% |
| North Metro Atlanta | 1 | 4.0% |
key developers and operators
top sponsors
| Sponsor | Projects |
| Digital Realty | 5 |
| Microsoft | 4 |
| Equinix | 3 |
| Atlas Development LLC | 2 |
| Amazon Web Services | 2 |
| 2 | |
| DC BLOX | 2 |
| Prologis | 1 |
| T5 Data Centers | 1 |
| Meta | 1 |
top operators
| Operator | Projects |
| Digital Realty | 5 |
| Microsoft | 4 |
| Equinix | 3 |
| Amazon Web Services | 2 |
| 2 | |
| DC BLOX | 2 |
| T5 Data Centers | 1 |
| Meta | 1 |
| QTS Realty Trust | 1 |
| CyrusOne | 1 |
project types
| Purpose | Count |
| ai-ml | 2 |
| cloud | 9 |
| colocation | 11 |
| enterprise | 2 |
| hyperscale | 19 |
complete project listing
All 25 documented projects in Georgia:
Click to expand full project table
| Project | Location | Status | Investment | Power | Sponsors |
| Project Bunkhouse | Stilesboro, Bartow | Planned | $19.0B | 1.8 GW | Digital Realty |
| Project Sail | Newnan, Coweta | Planned | $17.0B | 936 MW | Atlas Development LLC, Prologis |
| T5 Data Centers - Georgia Campus | Undisclosed, Unknown | Planned | $16.0B | 1.2 GW | T5 Data Centers |
| Amazon Web Services - Butts County Campus | Jackson, Butts | Planned | $5.5B | N/A | Amazon Web Services |
| Amazon Web Services - Douglas County Campus | Douglasville, Douglas | Planned | $5.5B | N/A | Amazon Web Services |
| Newton County Technology Park (Social Circle Technology Park) | Social Circle, Newton | Planned | $5.0B | N/A | TPA Group |
| Project Springbank | Adairsville, Bartow | Planned | $4.5B | 432 MW | Atlas Development LLC |
| Microsoft - Union City Campus | Union City, Fulton | Under Construction | $1.8B | 324 MW | Microsoft |
| Google - Douglas County Campus | Lithia Springs, Douglas | Operational | $1.2B | N/A | |
| Google - Monroe County Campus | Forsyth, Monroe | Planned | $1.1B | N/A | |
| Meta - Newton County Campus (Stanton Springs) | Social Circle, Newton | Expansion | $1.0B | N/A | Meta |
| Microsoft - Project Firecracker (Rome/Floyd County) | Rome, Floyd | Planned | $1.0B | N/A | Microsoft |
| QTS - Project Excalibur (Fayetteville) | Fayetteville, Fayette | Under Construction | $1.0B | N/A | QTS Realty Trust, Blackstone |
| CyrusOne - Douglas County Campus | Douglasville, Douglas | Operational | $200M | 50 MW | CyrusOne |
| DC BLOX - Atlanta East (Rockdale County) | Conyers, Rockdale | Under Construction | N/A | 144 MW | DC BLOX |
| DC BLOX - Atlanta West (Douglas County) | Lithia Springs, Douglas | Operational | N/A | 80 MW | DC BLOX |
| Digital Realty - ATL13 (Downtown Atlanta) | Atlanta, Fulton | Operational | N/A | 9 MW | Digital Realty |
| Equinix - AT1 (Downtown Atlanta) | Atlanta, Fulton | Operational | N/A | 4 MW | Equinix |
| Microsoft - East Point Campus | East Point, Fulton | Under Construction | N/A | N/A | Microsoft |
| Microsoft - Palmetto Campus | Palmetto, Fulton | Under Construction | N/A | N/A | Microsoft |
| Digital Realty - ATL15/ATL16 (Forest Park) | Forest Park, Clayton | Planned | N/A | N/A | Digital Realty |
| Digital Realty - ATL11 (Austell) | Austell, Douglas | Operational | N/A | N/A | Digital Realty |
| Digital Realty - ATL14 (Downtown Atlanta) | Atlanta, Fulton | Operational | N/A | N/A | Digital Realty |
| Equinix - AT2/AT3 (Downtown Atlanta) | Atlanta, Fulton | Operational | N/A | N/A | Equinix |
| Equinix - AT4 (North Atlanta) | Atlanta, Fulton | Operational | N/A | N/A | Equinix |
related pages