data center project cancellations analysis

on this page

Executive Summary

The data center industry experienced an unprecedented $89.7 billion in project cancellations in 2025, spanning 17 major facilities across 10 states. This wave of cancellations reveals systematic patterns in community opposition, regulatory failures, and misaligned incentive strategies that offer critical lessons for future project development.

Community opposition emerged as the dominant factor, accounting for 47% of cancelled value, signaling a fundamental shift in data center siting risk.

MetricValue
Total Cancelled Investment$89.7B+
Number of Projects17 facilities
States Affected10 states
Average Project Size$5.3B
Largest Single Cancellation$24.7B (Prince William Digital Gateway)

Major Cancellations

Prince William Digital Gateway (Virginia) - $24.7B

Date: August 2025 (formal termination Q4 2025) Location: Prince William County, VA Sponsors: QTS Realty Trust, Compass Datacenters Planned Capacity: 2 GW, 27 million sq ft Significance: Largest data center cancellation in history

Cancellation Timeline

  • 2023: Initial site acquisition, confidential discussions
  • January 2024: Public announcement
  • March 2024: County supervisors approve zoning
  • April-July 2024: Community opposition escalates
    • Resident groups file lawsuits
    • Environmental impact concerns raised
    • Water usage protests
  • August 2024: State-level intervention discussions
  • August 2025: QTS/Compass formally withdraw

Primary Factors

  1. Environmental Concerns:

    • Projected water usage: 1.5 million gallons/day
    • Impact on Occoquan Reservoir (regional water source)
    • Insufficient environmental impact analysis alleged
  2. Community Opposition:

    • Organized resident groups: “Save Prince William”
    • 15,000+ petition signatures
    • Traffic impact on suburban infrastructure
    • Noise concerns (generator testing, cooling equipment)
  3. Political Pressure:

    • State legislators questioned incentive package
    • County supervisor recall campaigns threatened
    • Virginia gubernatorial election factor
  4. Economic Factors:

    • Job creation estimates questioned (1,200 permanent jobs vs. land use)
    • Property tax impact analysis disputed
    • Comparison to residential development alternatives

Lessons:

  • Pre-announcement community engagement critical
  • Suburban sites near residential = high risk
  • Water usage mitigation must be comprehensive
  • Incentive transparency required

Wisconsin Cancellation Wave - $5.6B

Wisconsin experienced the most concentrated regional cancellations, with 4 major projects terminated in 2025.

Microsoft Caledonia - $4.0B (est)

Date: September 2025 Location: Racine County, WI (Caledonia township) Sponsor: Microsoft Planned Capacity: 500 MW

Cancellation Factors:

  • Community Opposition: Organized resistance from day one
    • “Preserve Caledonia” group formed pre-announcement
    • Concerns over rural character preservation
    • School district capacity impact questioned
  • Water Usage: 7 million gallons/day requested from Lake Michigan
    • Great Lakes Compact scrutiny
    • Chicago water rights implications
  • Agricultural Land Conversion: 1,200 acres farmland to industrial

Timeline:

  • March 2025: Microsoft announces intent
  • April 2025: County denies initial zoning change
  • May-August 2025: Negotiations attempt
  • September 2025: Microsoft withdraws

Additional Wisconsin Cancellations

Suburban Milwaukee Sites ($1.6B combined):

  • Brookfield project ($600M) - residential proximity
  • Waukesha project ($500M) - water utility denial
  • West Allis project ($500M) - zoning board rejection

Pattern: Suburban Milwaukee counties rejecting all major data center proposals


Indiana Suburban Rejections - $2.0B

Google Franklin Township - $1.0B

Date: June 2025 Location: Marion County, IN (Franklin Township) Sponsor: Google Planned Capacity: 300 MW

Cancellation Factors:

  • Zoning Denial: Township board vote 7-0 against rezoning
  • Community Mobilization: “Franklin Township Residents Alliance”
    • 3,500 residents attended zoning hearings (township pop. 45,000)
    • Organized email/call campaign to elected officials
  • Residential Proximity: Site bordered 3 subdivisions
  • Traffic Impact: Concerns over construction vehicle routes through residential

Outcome: Google shifted investment to Google-friendly New Carlisle campus expansion

Hancock County MegaSite - $1.0B

Date: July 2025 Location: Hancock County, IN Sponsor: Undisclosed hyperscaler Planned Capacity: 250 MW

Cancellation Factors:

  • Incentive Package Failure: State legislature did not approve requested $180M incentive
  • Community Opposition: Organized resistance in rural county
  • Site Preparation Costs: Sponsor unwilling to proceed without full incentive package

Significance: Demonstrates incentive package fragility


North Carolina Tract Mooresville - $30.0B

Date: Cancelled prior to 2025 (Q4 2024), impact realized in 2025 Location: Iredell County, NC (Mooresville area) Sponsor: Tract Planned Capacity: 1.5 GW Significance: Largest North Carolina project cancellation

Cancellation Factors:

  • Water Utility Denial: Mooresville Public Utilities denied capacity allocation
  • Community Mobilization: Lake Norman resident groups led opposition
  • Environmental Concerns: Impact on Lake Norman ecosystem
  • Timing: Withdrawal during due diligence phase (before formal announcement)

Impact: Shifted Tract focus to Arizona (Buckeye project still active)


Cancellation Patterns

By Primary Cause

Primary Reason% of Projects% of ValueTotal Value
Community Opposition47%49%$42.2B
Regulatory/Zoning Failure29%27%$26.0B
Failed Incentives24%24%$21.5B

By Geographic Pattern

Suburban Sites: 65% of cancellations

  • Proximity to residential areas = highest risk
  • Franklin Township, Caledonia, Prince William model

Greenfield Sites: 25% of cancellations

  • Agricultural/rural land conversion
  • “Preserve rural character” movements

Urban/Industrial Sites: 10% of cancellations

  • Lower cancellation rate
  • Hoffman Estates (former Sears HQ) = successful brownfield

By State

Highest Cancellation Concentrations:

  1. Virginia: $24.7B (1 mega-project)
  2. North Carolina: $30.0B (1 mega-project)
  3. Wisconsin: $5.6B (4 projects)
  4. Indiana: $2.0B (2 projects)

States with Zero Cancellations in 2025:

  • Georgia (grid expansion approval helped)
  • Arizona (proactive community engagement)
  • Texas (industrial site focus)

Community Opposition Analysis

Opposition Organization Tactics

Successful Opposition Groups Share:

  1. Early Mobilization

    • Form before/immediately upon announcement
    • Secure legal counsel early
    • Establish 501(c)(3) or (c)(4) organization
  2. Multi-Pronged Strategy

    • Petition campaigns (targeting elected officials)
    • Zoning hearing testimony (packing hearings)
    • Litigation threats (environmental process challenges)
    • Media campaigns (local + regional coverage)
  3. Coalition Building

    • Residential associations
    • Environmental groups
    • Agricultural/farmland preservation organizations
    • Fiscal watchdog groups (questioning incentives)
  4. Technical Arguments

    • Water usage impact studies
    • Traffic impact assessments
    • Property value impact analysis
    • School capacity strain projections

Common Opposition Themes

Environmental:

  • Water consumption (repeatedly cited #1 concern)
  • Energy demand impact on grid
  • Noise pollution (generators, cooling)
  • Light pollution (24/7 operations)

Economic:

  • Property value impact fears
  • Questioned job creation (low permanent employment)
  • Tax incentive cost-benefit analysis
  • Infrastructure burden (roads, schools, utilities)

Quality of Life:

  • Rural/suburban character preservation
  • Traffic during construction + operations
  • Noise from cooling systems, diesel generators
  • 24/7 operations in residential areas

Regulatory Failure Patterns

Zoning Process Breakdowns

Common Failure Points:

  1. Inadequate Community Engagement Before Filing

    • Projects announce + file zoning simultaneously
    • Community feels blindsided
    • Opposition organizes during comment period
  2. Insufficient Environmental Review

    • Water usage impacts under-analyzed
    • Traffic impact studies inadequate
    • Noise impact not addressed
  3. Incentive Package Transparency

    • Confidential negotiations revealed late
    • Public backlash to “secret deals”
    • Legislative approval required but not secured
  4. County vs. State Conflicts

    • County approval, but state environmental/water denial
    • Misalignment on economic development priorities

Successful Avoidance Strategies

Projects That Avoided Cancellation:

Stargate Abilene (TX):

  • Industrial site (former airport)
  • No residential proximity
  • On-site power generation (grid impact minimized)
  • Proactive City of Abilene partnership

Compass Hoffman Estates (IL):

  • Brownfield (former Sears HQ)
  • No agricultural land conversion
  • Industrial zoning already in place
  • Major employer replacement narrative

AWS Richmond County (NC):

  • Rural county eager for development
  • Industrial site selection
  • Multi-year community engagement pre-announcement
  • Water solution addressed upfront (on-site wells + treatment)

Economic Impact Analysis

Lost Investment

Total Cancelled Investment: $89.7B

Economic Multiplier Effects Lost (estimated):

  • Construction jobs: 187,000 job-years
  • Permanent jobs: 14,600
  • Supplier/service jobs: 22,000
  • Tax revenue (10-year): $4.2B

Geographic Distribution of Loss

States Most Impacted:

  1. Virginia: $24.7B lost investment
  2. North Carolina: $30.0B lost investment
  3. Wisconsin: $5.6B lost investment

Regional Impacts:

  • Mid-Atlantic: $35B+ (VA, NC)
  • Midwest: $8B+ (WI, IN, IL)

Where Investment Relocated

Beneficiary States (from cancelled projects):

  • Arizona: Tract shifted from NC to AZ
  • Georgia: Projects reconsidering after grid approval
  • Texas: General shift to deregulated, pro-growth states

Lessons for Successful Development

Pre-Announcement Phase

Critical Success Factors:

  1. Community Engagement BEFORE Announcement

    • 6-12 months of stakeholder meetings
    • Identify concerns early
    • Build support coalitions (chambers, economic development)
  2. Site Selection Criteria

    • Prioritize: Brownfield, industrial, non-residential
    • Avoid: Greenfield suburban, agricultural conversion
    • Water: Verify utility capacity + permitting before announcement
  3. Environmental Due Diligence

    • Complete full impact assessment internally
    • Identify mitigation strategies
    • Budget for environmental infrastructure (wells, treatment, etc.)

Announcement Phase

Best Practices:

  1. Transparency on Impacts

    • Honest water usage projections
    • Realistic job creation numbers (construction vs. permanent)
    • Traffic mitigation plans presented upfront
  2. Benefits Communication

    • Emphasize local hiring commitments
    • Supplier/contractor opportunities
    • Community investment programs (schools, infrastructure)
  3. Elected Official Alignment

    • Secure county + state support pre-announcement
    • Understand approval process timeline
    • Verify incentive package legislative viability

Regulatory Process

Navigation Strategy:

  1. Robust Environmental Impact Statement

    • Address water, traffic, noise comprehensively
    • Independent third-party analysis
    • Public comment response plan
  2. Zoning Hearing Preparation

    • Organize supporter testimony
    • Technical expert witnesses
    • Visual simulations (showing minimal site impact)
  3. Incentive Package Design

    • Transparent cost-benefit analysis
    • Clawback provisions (job creation, investment milestones)
    • Regular public reporting requirements

Forward Outlook

Trend Implications

2026 Expectations:

  • Continued Cancellations in suburban markets
  • Shift to Industrial/Brownfield sites accelerating
  • Community Engagement becoming 12-18 month process (from 3-6 months)

High-Risk Profiles

Projects Likely to Face Cancellation Risk:

  • Suburban greenfield sites
  • Agricultural land conversion
  • States without proactive utility grid expansion
  • Projects relying on confidential incentive negotiations

Low-Risk Profiles

Projects Likely to Succeed:

  • Industrial brownfield redevelopment
  • Sites with existing infrastructure
  • States with grid expansion programs approved
  • Projects with 12+ months pre-announcement community engagement

State-Level Responses

Pro-Data Center Legislation

States Passing Supportive Laws (2025):

  • Arizona: Streamlined permitting for data centers >$1B
  • Georgia: Data center grid expansion enabling legislation
  • Texas: ERCOT fast-track interconnection for >500 MW loads

Restrictive Legislation/Moratoria

States/Localities with New Restrictions:

  • Maryland: Montgomery County 18-month moratorium
  • Colorado: Jefferson County requires supermajority for data center zoning
  • Wisconsin: Multiple townships adopting restrictive ordinances
  • Maine: 650 MW statewide generation limit for data centers


Last Updated: December 30, 2025 Data Sources: Project announcements, local government minutes, news reports, developer interviews

on this page