nuclear partnerships for data centers
on this page
Overview
Nuclear energy has emerged as the strategic solution to data centers’ insatiable power demands and carbon-free commitments. In 2024-2025, $12+ billion has been committed to data center-dedicated nuclear projects, representing the largest private investment in U.S. nuclear infrastructure since the 1980s.
Two Models Emerging:
- Small Modular Reactors (SMRs): New construction, 50-300 MW units
- Reactor Restarts: Bringing recently-closed nuclear plants back online
| Metric | Value |
| Total Committed Investment | $12+ billion |
| Number of Partnerships | 9 major agreements |
| Total Planned Capacity | 6.5+ GW |
| SMR Projects | 5 facilities |
| Reactor Restart Projects | 3 facilities |
| Hyperscalers Involved | Google, Microsoft, Amazon |
Major Partnerships
Google-TVA-Kairos Power (Tennessee)
Announced: October 2025 Capacity: 50 MW (initial), expandable to 500 MW Technology: Kairos Power Hermes SMR (molten salt-cooled) Location: Oak Ridge, Tennessee area Timeline: First reactor operational by 2030
| Component | Details |
| Investment | $1.5B (Google contribution undisclosed) |
| Reactor Type | Fluoride salt-cooled high temperature |
| Google Commitment | 25-year power purchase agreement |
| TVA Role | Site host, operator, grid integration |
| Kairos Role | Reactor design, construction, licensing |
Significance:
- First hyperscaler-utility-vendor SMR partnership in U.S.
- Google’s carbon-free energy commitment (24/7 by 2030)
- TVA returning to nuclear construction after decades
Technical Innovation:
- Molten salt cooling: Higher efficiency than water-cooled
- Walk-away safe: Passive safety systems (no active cooling required)
- Modular construction: Factory-built, site-assembled
- Fuel flexibility: Can use HALEU (high-assay low-enriched uranium)
Development Milestones:
- 2025 Q4: NRC license application submission
- 2026-2028: NRC review process
- 2028: Construction commencement
- 2030: First unit operational
- 2032-2035: Expansion to 500 MW (10 units)
Google Data Center Integration:
- Location: Tennessee data center cluster (existing + planned)
- Dedicated offtake: 100% of power to Google facilities
- Grid backup: TVA grid provides redundancy
- Renewable complement: Solar + storage augmentation
Microsoft-Constellation Three Mile Island Restart
Announced: September 2024 (advancing through 2025) Capacity: 835 MW (Unit 1) Location: Londonderry Township, Pennsylvania Timeline: Operational 2028
| Component | Details |
| Investment | $1.6B restart costs |
| Microsoft PPA | 20 years, 100% offtake |
| Original Closure | 2019 (economic reasons) |
| Restart Timeline | 4 years (2024-2028) |
| Renamed | Crane Clean Energy Center |
Why Three Mile Island?
- Recently closed (2019) - infrastructure intact
- Strong safety record since 1979 incident (Unit 1 unaffected)
- PJM interconnection - existing transmission
- Pennsylvania location - proximity to East Coast data centers
Restart Process:
- 2024: Constellation announces intent, Microsoft PPA signed
- 2025: NRC restart review initiated
- Safety systems inspection
- Equipment certification
- Environmental review
- 2026-2027: Refurbishment work
- Steam generators replacement
- Control systems upgrade
- Cooling systems restoration
- 2028: Operational restart
Microsoft Data Center Integration:
- Pennsylvania data center cluster: Multiple facilities powered
- Carbon-free goal: Eliminates need for renewable energy certificates (RECs)
- 24/7 matching: Nuclear provides constant baseload (vs. intermittent renewables)
- Grid independence: Reduces reliance on constrained PJM grid
Economic Impact:
- Jobs: 3,400 during refurbishment, 600 permanent operations
- Local economy: $3B economic impact over 20 years
- Tax revenue: $1B+ to Pennsylvania over PPA term
Amazon-Energy Northwest (Washington)
Announced: October 2024 Capacity: 4 SMRs, 320 MW total (80 MW each) Technology: X-energy Xe-100 SMR (high temperature gas-cooled) Location: Near Columbia Generating Station, Washington Timeline: First unit 2029, full deployment 2032
| Component | Details |
| Investment | $2.0B (Amazon portion) |
| Reactor Type | Xe-100 high temperature gas-cooled |
| Fuel | TRISO (tristructural isotropic) pebbles |
| Amazon Commitment | Right to purchase up to 960 MW (12 units) |
| Energy Northwest | Operator, existing nuclear site |
Strategic Rationale:
- AWS US-West region: Proximity to Oregon/Washington data centers
- Baseload carbon-free: Complements existing hydropower (Columbia River)
- Scalability: Modular deployment (4 units initially, up to 12 potential)
X-energy Xe-100 Technology:
- TRISO fuel: Inherently safe (cannot melt down)
- High temperature: 750°C outlet temp (vs. 300°C light water reactors)
- Small footprint: 80 MW each, factory-assembled
- Passive cooling: No active systems required for shutdown
Deployment Plan:
- Phase 1 (2029): 2 units, 160 MW
- Phase 2 (2031): 2 additional units, 160 MW
- Phase 3 (2032+): Up to 8 more units (640 MW)
Amazon-Dominion Energy (Virginia)
Announced: November 2024 Capacity: Exploring “multiple gigawatts” near existing nuclear plants Location: Louisa County, Virginia (near North Anna nuclear station) Timeline: Feasibility study 2025-2026
Focus:
- Data center cluster: Louisa County emerging as Virginia’s next major hub
- Existing infrastructure: Leverage North Anna transmission
- SMR deployment: Likely 6-10 SMR units (500-1000 MW total)
Status: Feasibility + site studies underway
Pennsylvania Nuclear Corridor
Multiple projects exploring nuclear integration in Pennsylvania, creating a “nuclear corridor” for data centers.
Susquehanna Nuclear Station Proximity Projects
Homer City Energy Campus (4.5 GW planned):
- Location: 45 miles from Susquehanna nuclear plant
- Strategy: Grid connection to nuclear baseload
- Status: Planned, permitting stage
TECfusions Keystone Connect (3 GW):
- Location: Northeast Pennsylvania
- Nuclear proximity: Susquehanna + Limerick
- Status: Under construction
Project Jupiter (New Mexico) Nuclear Component
Planned Addition: 500 MW SMR Timeline: 2027-2030 feasibility, 2030+ deployment Technology: Vendor selection in progress (NuScale, X-energy, or Kairos finalists) Rationale: On-site baseload for AI training workloads
Small Modular Reactor (SMR) Technology
Leading Vendors
1. NuScale Power
- Design: Light water SMR, 77 MW per module
- Status: First NRC design certification (January 2023)
- Projects: Utah UAMPS project (delayed), evaluating data center market
- Advantages: Proven light water technology, certified design
- Challenges: Higher cost than competitors, smaller capacity per unit
2. X-energy
- Design: Xe-100, high temperature gas-cooled, 80 MW
- Status: NRC design certification review underway
- Projects: Amazon-Energy Northwest (Washington)
- Advantages: TRISO fuel safety, high temperature efficiency
- Challenges: New fuel form factor (supply chain development)
3. Kairos Power
- Design: Hermes, molten salt-cooled, 50 MW (scalable)
- Status: NRC application submitted October 2025
- Projects: Google-TVA (Tennessee)
- Advantages: Highest temperature (efficiency), walk-away safety
- Challenges: Novel design (longer NRC review expected)
4. TerraPower (Bill Gates)
- Design: Natrium, sodium-cooled fast reactor, 345 MW
- Status: Demonstration project in Wyoming
- Projects: Not yet data center-specific, but evaluating
- Advantages: Large capacity per unit, molten salt energy storage integration
- Challenges: Sodium cooling complexity
SMR Economics
Capital Costs:
- Per unit: $400M - $1.2B (depending on design, 50-350 MW)
- Per kW: $5,000 - $7,000/kW (higher than conventional nuclear)
- Learning curve: Expected 30-40% cost reduction by 10th unit (factory production)
Operational Costs:
- Fuel: $15-20/MWh (vs. $40-60/MWh natural gas)
- O&M: $10-15/MWh
- Total LCOE: $60-80/MWh (first units), declining to $40-55/MWh (at scale)
Data Center Value Proposition:
- 24/7 carbon-free: Eliminates REC purchases ($20-40/MWh)
- Price certainty: 40-60 year reactor life (vs. volatile gas prices)
- Grid independence: Reduces interconnection queue risk
Reactor Restart Economics
Three Mile Island Model
Restart Costs: $1.6B total
- Equipment replacement: $800M (steam generators, turbines)
- Systems upgrades: $400M (control systems, safety)
- Licensing/permitting: $200M (NRC fees, environmental)
- Contingency: $200M
Cost Comparison:
- Per kW: $1,900/kW (vs. $5,000-7,000 for new SMR)
- Timeline: 4 years (vs. 7-10 years new construction)
- Economics: Highly favorable for recently-closed plants
Restart Candidates (closed within 10 years):
| Plant | State | Capacity | Closed | Restart Feasibility |
| Three Mile Island | PA | 835 MW | 2019 | In progress (Microsoft) |
| Duane Arnold | IA | 615 MW | 2020 | Study underway (Google/QTS) |
| Indian Point 2 | NY | 1,028 MW | 2020 | Low (political opposition) |
| Indian Point 3 | NY | 1,041 MW | 2021 | Low (political opposition) |
| Pilgrim | MA | 685 MW | 2019 | Low (decommissioning started) |
Duane Arnold (Iowa) - Under Evaluation
Status: Feasibility study initiated Q4 2025 Drivers: Google Iowa ($7B), QTS Cedar Rapids ($10B), Microsoft West Des Moines Combined data center load: 2+ GW by 2030
Restart Economics:
- Cost estimate: $1.2B
- Timeline: 2026-2029 (if approved)
- PPAs: Google, Microsoft, QTS negotiating 25-year agreements
- Viability: High (strong PPA interest, intact infrastructure)
Industry Implications
Carbon-Free Energy Achievement
Hyperscaler Carbon-Free Goals:
- Google: 24/7 carbon-free by 2030
- Microsoft: Carbon negative by 2030
- Amazon: Net-zero carbon by 2040
Nuclear’s Role:
- 24/7 generation: Unlike wind/solar (intermittent)
- No RECs needed: Direct carbon-free power (vs. market-based credits)
- Baseload match: Constant data center load requires constant generation
Impact:
- Renewable displacement? No - nuclear complements renewables
- Grid stability: Nuclear provides baseload, renewables provide marginal
Grid Independence
Interconnection Queue Crisis:
- PJM: 3-5 year queue for large loads
- ERCOT: 70 GW backlog
- CAISO: Similar constraints
Nuclear Solution:
- On-site generation: Bypasses queue entirely
- Behind-the-meter: Direct connection (vs. grid interconnection)
- Timeline certainty: 4-7 years (vs. 5-10 years grid-dependent)
Investment Scale
Total 2024-2030 Nuclear for Data Centers:
- SMR deployments: $8.0B (5 projects)
- Reactor restarts: $4.0B (2-3 projects)
- Total committed: $12.0B+
- Potential pipeline: $25B+ (additional announced studies)
Comparison:
- Utility grid expansions for data centers: $52B (2024-2030)
- Nuclear share: 23% of total infrastructure investment
Regulatory Pathway
NRC Licensing Process
SMR Design Certification:
- Pre-application (1-2 years): Vendor engagement with NRC
- Formal review (3-5 years): Design certification application
- Certification (upon completion): 15-year design approval
Construction&Operating License (COL):
- Site-specific review (2-3 years): Environmental, safety analysis
- Combined license issued: Allows construction + eventual operation
- ITAAC completion: Inspections, tests, analyses, and acceptance criteria
Total Timeline: 7-10 years from concept to operation (first unit)
Accelerated pathways:
- Fleet deployment: 2nd+ unit 4-5 years (vs. 7-10 first)
- Reactor restarts: 4-5 years (existing license modification)
Environmental Review
NEPA Process:
- Environmental Impact Statement (EIS) required
- Public comment period: 60-90 days
- Common concerns: Water usage, thermal discharge, waste storage
Data Center-Nuclear Integration:
- Co-location advantage: Single EIS for facility + power (vs. separate reviews)
- Cooling synergy: Data center waste heat + nuclear cooling optimization
Challenges & Risks
Technical Challenges
SMR Deployment:
- First-of-a-kind risk: New designs have construction/operational unknowns
- Supply chain: HALEU fuel production limited in U.S.
- Workforce: Limited SMR construction/operation experience
Reactor Restarts:
- Equipment degradation: Extended closure may require more extensive refurbishment
- Regulatory: NRC scrutiny on safety systems after extended shutdown
- Public perception: Historical incident concerns (e.g., TMI name recognition)
Economic Risks
Cost Overruns:
- Nuclear history: Conventional reactors typically 2-3x over budget
- SMR promise: Factory construction should reduce, but unproven
- Mitigation: Fixed-price PPAs shift risk to generator
Competitive Pressure:
- Renewable costs declining: Solar + storage approaching $40/MWh
- Nuclear LCOE: $60-80/MWh (SMR first units)
- Counter: 24/7 matching value + grid independence premium
Political/Social Risks
Nuclear Opposition:
- Environmental groups: Some oppose nuclear expansion
- Local resistance: Waste storage concerns, safety fears
- Mitigation: Data center community engagement lessons apply to nuclear component
Waste Management:
- No permanent repository: Yucca Mountain cancelled
- On-site storage: SMRs produce less waste (smaller cores)
- Solution horizon: 40-60 year reactor life outlasts current waste storage debate
Forward Outlook
2026-2030 Projections
SMR Deployments:
- Confirmed: 5 projects, 1.2 GW, $8B
- Probable: 8-10 additional projects, 2-3 GW, $12-15B
- Possible: 20+ projects by 2030 (if early projects succeed)
Reactor Restarts:
- Confirmed: TMI Unit 1, 835 MW, $1.6B
- Probable: Duane Arnold, 615 MW, $1.2B
- Possible: 2-3 additional (if market develops)
Total 2030 Data Center Nuclear Capacity:
- Conservative: 3 GW ($12B invested)
- Base case: 6 GW ($25B invested)
- Bullish: 10+ GW ($40B+ invested)
Technology Evolution
Next-Generation SMRs (2030+):
- Microreactors: 1-20 MW (single data center facility)
- Advanced fuels: Accident-tolerant fuels (longer refueling cycles)
- Hybrid systems: Nuclear + hydrogen production + data center loads
Related Pages
Last Updated: December 30, 2025 Nuclear partnership data current as of December 2025 Next Update: Q2 2026 (following Kairos/Google NRC application milestone)