power grid topology

overview

a hyperscale data center requires 100mw to 1gw of power—comparable to a medium-sized city. this cannot be delivered through urban distribution infrastructure.

transmission vs distribution

voltage levels

  • transmission: 115kv-765kv (bulk power, long-distance)
  • subtransmission: 33kv-138kv (intermediate)
  • distribution: 4kv-35kv (local delivery to buildings)
  • secondary: 240v/415v (to individual premises)

capacity differences

  • distribution designed for neighborhood-scale loads (residential, small commercial)
  • hyperscale requires direct transmission tap at 138kv+
  • urban substations are space-constrained and capacity-limited

why 500mw cannot use urban distribution

physical impossibility

  • urban distribution wires are thermally limited for neighborhood-scale loads
  • drawing 500mw-1gw would cause catastrophic thermal failure
  • existing urban wires lack current-carrying capacity

the straw analogy

urban distribution is like drinking a lake through a straw. the water (power) exists, but the delivery mechanism (distribution wires) cannot physically handle the volume.

what urban upgrade requires

  1. build new high-voltage transmission corridors through neighborhoods
  2. acquire land for massive substations (urban land: $500k-1m+/acre)
  3. excavate city streets (navigating gas, water, sewer lines)
  4. underground high-capacity cables
  5. timeline: 48-72+ months minimum

rural alternative

  1. tap existing transmission line in rural corridor
  2. build greenfield substation on $10k-30k/acre land
  3. connect directly at 138kv+
  4. timeline: 18-36 months

substation economics

factorurbanrural
land cost/acre$500k-1m+$10k-30k
configurationindoor (gis required)outdoor (ais possible)
new substation cost$15-50m+$3-7m
timeline48-72 months18-36 months

gis = gas-insulated switchgear (10-20% footprint of air-insulated, but expensive)

ais = air-insulated switchgear (standard, cost-effective)

case study: northern virginia

northern virginia (data center alley) exemplifies grid constraints:

  • 250+ data centers, ~6,000mw active
  • transmission grid in eastern loudoun county now constrained
  • dominion energy: 7-year wait for new large customer connections
  • july 2024: lightning strike on 230kv line caused 1,500mw of data centers to switch to backup

sources

  • miso transmission cost estimation guide
  • dominion energy investor presentations
  • pjm interconnection data
  • iec 60038 voltage standards
on this page