development timelines

overview

in data center development, time is the most valuable resource. a 12-month delay can compress project irr by 200-300 basis points. developers pay premiums for sites with existing power capacity specifically to avoid interconnection delays.

development timeline comparison

phasegreenfieldbrownfield
site acquisition3-6 months6-12 months
interconnection18-36 months48-72+ months
permitting6-12 months12-24 months
construction12-18 months18-24 months
total3-5 years5-8+ years

key bottleneck: interconnection queue (3-7+ years) exceeds construction time.

hyperscaler capital expenditure (2024-2025)

company2024 capex2025 capexgrowth
microsoft$50-65b~$80b+45%
google$49-52b$91-93b+80%
amazon~$75b$118-125b+60%
meta~$60b$70-72b+17%

aggregate 2025: $315-392b (top 11 hyperscalers)

this capital seeks deployment—delays mean lost opportunity.

ai infrastructure demand growth

  • ai data center market: $236b (2025) to $934b (2030) = 31.6% cagr
  • global dc ai capacity: 33% (2025) to 70% (2030)
  • 10gw breaking ground in 2025; 7gw targeted for completion

development returns

metricvalue
digital realty yield on cost11-14%
equinix wholesale returns~30% (historical)
developer hurdle rate12-19% irr
development profit margin40-50%+
cap rates (2025)mid-4% to mid-6%

the cost of delay

operational downtime costs

  • per-minute: $5,600 average (gartner)
  • per-hour: $140,000-$540,000
  • 90-minute outage: >$505,500 in lost revenue

construction delay costs

for a 100mw facility @ $175/kw-month lease rate:

  • monthly revenue at stabilization: $17.5m
  • 12-month delay = $210m in foregone revenue
  • plus financing costs on drawn capital

interconnection delay costs

  • pjm transmission costs (2024): $4.3b passed to ratepayers
  • virginia portion: $1.98b
  • capacity auction inflation: $2.2b to $14.7b (single year)

the time premium calculation

sites with existing transmission capacity command premiums because:

  • 3-year interconnection queue effectively capitalizes into land price
  • paying 5x farmland value ($50k vs $10k/acre) is rational if it secures 2-year speed advantage
  • on 100mw campus: 2-year acceleration = $400m+ in earlier revenue

speed strategies

behind-the-meter generation

  • bypass queue entirely
  • 2-3 year timeline vs 5-7+ years
  • 54.5% of gigawatt projects use this approach

modular/prefabricated construction

  • 50% construction time reduction
  • up to 50% irr improvement
  • roi timeline shortened by ~1 year

xai colossus example

  • repurposed electrolux factory
  • completed in 122 days
  • 150mw power supply approved nov 2024
  • xai paid for new substation construction

financial model impact

base case (100mw)

  • total capex: $1.15b ($11.5m/mw)
  • build period: 24 months
  • stabilized annual noi: ~$270m
  • yield on cost: ~23.4%
  • levered irr: 35.5%

12-month delay scenario

  • additional financing cost: ~$50m
  • foregone revenue: ~$210m
  • irr compression: 200-300 bps

sources

  • gartner downtime cost analysis
  • morgan stanley hyperscaler research
  • digital realty & equinix investor presentations
  • cbre data center trends reports
  • mordor intelligence market sizing
on this page